Original source · versioned page text
2015-08-24 General Committee Agenda
Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.
GENERAL COMMITTEE MEETING AGENDA 24 AUGUST 2015
Page 32 of 40
GENERAL COMMITTEE MEETING AGENDA 24 AUGUST 2015
Capital / Operating Capital
Sum of Proposed Budget Carryover Revenue / Expense
CAPEX PROGRAM Cost Centre / Project Description Details Expense Revenue Grand Total
Fleet Whole of Shire Plant Replacement Program Actual replacement program varied throughout the year due to 454 466 454,466
emerging issues and opportunities pursued. Carryover funds to be
used to progress leased vehicle replacement program.
Fleet Total 454,466 454,466
Holiday Parks Cooroy RV Stopover In progress - Not yet complete 32,949 32,949
Noosa River Holiday Park Design phase not complete 13,281 13,281
Holiday Parks Total 46,230 46,230
IT Whole of Shire Tech One HR Module Implementation deferred due to resourcing constraints during 105,990 105,990
2014/15 and focus on other priorities.
IT Total 105,990 105,990
Parks & Playgrounds Re-lining of Ben Lexcen stormwater Initial estimates indicate more funds required and the volume of 28,257 28,257
damaged connected pipes has significantly increased, currently
request for Quotes have recently been received and are being
assessed.
Tewantin Splash Park Playground Renewal This project has commenced planning and quotations and was a 130,000 130,000
late project at the end of the 14/15 financial year.
Parks & Playgrounds Total 158,257 158,257
Pathways & Enabling Facilities Gibson Road (Eumindi Noosa Rd to Thomas St) - On road cy Carryover required for resumption and remaining footpath works yet 15,000 15,000
to be completed - $15,000 to be allocated to outstanding Land
acquisition.
Noosa Heads - Park Road boardwalk design Commenced - Carried over in 15/16 to ensure that Council is 156,865 156,865
construction ready for 16/17.
Sunrise Beach - Ben Lexcen Dr school Grant funded project 2015/2016 and funds will be required to 45,716 45,716
support construction activities.
Pathways & Enabling Facilities Total 217,581 217,581
Public Transport Infrastructure Electric Bus Charging Station and Installation Funds are committed for the installation of the charging stations. 77,910 77,910
Electric Bus Feasibility Study Still outstanding works to be completed before project can be 4366 - (50,000) - (45,634)
completed including commitments that have been raised.
Noosa Bus Station Safer Streets Program Still outstanding works to be completed to have the CCTV 50,291 - (57,900) - (7,609)
operational.
Public Transport Infrastructure Total 132,567 - (107,900) 24,667
Sealed Roads Network Dr Pages - Kinmond Creek Rd Initial Planning & Design Continuation and finalisation of design funds committed - this project 75,055 75,055
was anticipated to continue into 15/16.
Sealed Road Pavement surveys and Investigations Still outstanding work to be completed with condition data as a result 39,064 39,064
in delays with contractor.
Tewantin Cooroy Noosa Rd Stages 2-6 Design Only This project was planned to carryover into 15/16 and has recently 120,986 120,986
attracted grant funding approval.
Whole of Shire - pavement surveys Funds required to undertake more pavement designs once 19,687 19,687
condition analysis is completed.
Whole of Shire - reseal and rehab This amount needs to allocate approx. $318k to Gibson road 1,378,679 1,378,679
project. Remaining funds will be utilised for the projects that were
not completed in 2014/15.
Sealed Roads Network Total 1,633,471 1,633,471
Sports Ground and Facilities Girraween Sports Complex Lighting Still outstanding works to be completed to install the system - this 10,000 10,000
has now been allocated to Council's electrician.
Sports Ground and Facilities Total 10,000 10,000
Stormwater Drainage Gympie Terrace pipe rehabilitation Delays in the specifications and that the pipes could not be religned 194,386 194,386
has extended the length of the design phase.
Gympie Terrace Pipe Rehabilitation - Investigation & Design The Culvert in Thomas street requires a more detailed specifications 10,763 10,763
and method of works before we can commence construction.
Page 32 of 40See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.