GENERAL COMMITTEE MEETING AGENDA 24 AUGUST 2015
Page 33 of 40
GENERAL COMMITTEE MEETING AGENDA 24 AUGUST 2015
Capital / Operating Capital
Sum of Proposed Budget Carryover Revenue / Expense
CAPEX PROGRAM Cost Centre / Project Description Details Expense Revenue Grand Total
Stormwater Drainage Whole of Shire - Flood mitigation stage Daintree Estate & Pomona Rifle St In progress, carry over funds. 2,097,747 - (802,072) 1,295,675
Daintree nearing completion. Pomona delayed due to property
resumption matters.
Whole of Shire - stormwater structures Delays were incurred due to resourcing staff due staff illness and 47,581 47,581
appointments. Funds will be consolidated with 15/16 program to
deliver a greater volume of structures to be replaced.
Stormwater Drainage Total 2,350,477 - (802,072) 1,548,405
Streetscapes and Road Corridors Cooroy Noosa Road Corridor Improvement Carryover, still outstanding commitments and signage required to 88,554 - (28,750) 59,804
complete this stage.
Peregian Beach - precinct planning Carry over - more community consultation required and impacts on 29,618 29,618
surrounding developments to be considered.
Rufous St Design & Development Phase Carry over funds required to continue the concept planning 13,167 13,167
activities.
Rufous St Precinct Redevelopment Demolition of existing buildings completed. Original estimate - -
insufficient - Additional funds required for demolition including
asbestos removal and temporary fencing. No funds required for
15/16 for this stage of project.
Streetscapes and Road Corridors 131,339 - (28,750) 102,589
Total
Transport and Infrastructure Manag __ Eenie Creek Pathway Stage 1 Signage Project delayed and remaining funds are required to pay for the 19,003 - (10,000) 9,003
works recently completed. This project is also supported by grant
funding.
Noosa Junction Transit Centre - improve Works have been delayed as Council negotiates with translink and 40,000 - (20,000) 20,000
DTMR.
Standards Review - Standard Drawings Ongoing works required for Council to continue and update the suite 13,791 13,791
of standard drawings for our infrastructure.
Whole of Shire Traffic Study Traffic study is ongoing and was delayed due to staff vacancies. 41,201 41,201
Project is progressing and the remaining carryover funds have been
committed.
Weyba Road Reef Street Intersection Improvements - PIP Carry over - this project has attracted TIDS project for 15/16 and 104,480 104,480
also cycle grant funding for 2015/16.
Transport and Infrastructure 218,474 - (30,000) 188,474
Management Total
Waste Management Noosaville Landfill - Dosing & Monitoring Equipment Carry over - pending advice from DEHP / Council Env Officer 120,000 120,000
Waste Management Total 120,000 120,000
Grand Total 8,059,208 - (968,722) 7,090,486
Page 33 of 40See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.