                                                                                        2007/1894



9    The Consulting Engineers for the project shall be currently Registered Professional Engineers
     of Queensland (RPEQ). The Consulting Engineers are responsible for arranging all
     inspections with Council’s Construction Technical Officer or nominated staff.
10   Prior to works commencing, Council is to be advised of the Engineer (RPEQ) supervising the
     project. (This person will be the contact for the project).
11   An inspection is to be carried out with the relevant Council officers, the Contractor and
     Supervising Engineer after road centrelines have been established, and prior to clearing being
     carried out. This inspection is to deal with the limits of clearing to be carried out for this
     development. This meeting is to take place prior to the “Pre-start” meeting.
12   Council standards shall apply to these works unless otherwise modified herein.
13   The person acting on this permit shall ensure that its consultants and contractors take all
     reasonable care during the construction of the engineering works to ensure that Council
     property, road pavements or facilities (such as underground drainage, water supply,
     sewerage, footpaths, kerbing, landscaping, street furniture etc.) are protected against any
     damage or interference whatsoever.
     If any Council property or facilities should be damaged by the Applicant or any of its
     Consultants or Contractors through any cause whatsoever in the course of, directly or
     indirectly, carrying out the engineering works, the Applicant and/or its Contractors shall
     forthwith notify the Chief Executive Officer, Sunshine Coast Regional Council, and shall
     forthwith rectify the damage to that property or facility at its cost and to the satisfaction of the
     Chief Executive Officer, Sunshine Coast Regional Council.
     All rectification works are to be completed prior to the commencement of the use or,
     alternatively, the Applicant may request the Council to carry out the rectification work at the
     Applicant’s cost, such cost being paid by the Applicant to Council prior to the commencement
     of the use.
     In the case of any emergency Council shall be entitled to rectify such damage at the cost of
     the Applicant, such cost being paid prior to the commencement of the use.
14   The development of the site shall be carried out in such a manner as to prevent dust and/or
     sand nuisance to residents and/or tenants in the vicinity of the development.
15   Construction work and other associated activities are permitted only during the hours of 7.00
     am and 6.00 pm Monday to Saturday. No work is permitted on Sundays or public holidays,
     except where extended hours are approved by Council’s CEO.
16   All signage, including that for safety during construction shall be in accordance with the
     Manual of Uniform Traffic Control Devices and Transport Infrastructure (Roads) Act.
17   Safe pedestrian access on Kingfisher Drive in the vicinity of the development shall be
     maintained at all times. Should footpath / road closures be necessary to carry out construction
     works, Council’s Construction Technical Officer (ph 0410 512 505) must be notified prior to the
     proposed closure.
18   Sediment and erosion control measures must be in place prior to works commencing. If such
     measures are not in place or are not satisfactory, “on the spot “fines may be issued. Such
     fines can be issued if sediments from the site are found to enter or have the potential to enter
     Council’s stormwater system or natural waterways. Although the sediment and erosion control
     measures have been approved on drawing No.17282-OW1-B, it is the site's supervising
     engineer who is responsible for ensuring that the sediment and erosion control measures have
     been designed by an RPEQ or CPESC and constructed:
     i.    In accordance with "best practice" methods,
     ii.   Revised by an RPEQ or CPESC to address the issues raised by changes in the
           projected construction schedule and methods,

                                                                                       Page 3 of 7

Used in these records

About this file

File size
57 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

001A849F.001.pdf · 57 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.