Flows up to and including the major Q100 storm event will be conveyed
to and attenuated by the proposed attenuation tanks. Inspection of Excel
screenshots (Appendix E) demonstrates that attenuation of stormwater
runoff to pre-developed levels is achievable for all proposed sub-
catchments.
A total attenuation volume of 5kL will be required under covenant for
each proposed townhouse/residential dwelling with a further 3kL of
storage to be made available for indoor non-potable and outdoor
irrigation reuse (8kL total) with low flow pipes sized to provide non-
worsening of peak discharge volumes for a range of storm events.
Please refer to the attached engineering drawings in Appendix C for
locations and details of proposed attenuation measures.
6.4 Stormwater Quality Management
The site currently consists of 100% pervious land with significant tree/shrub
cover. The proposed development will result in ≤ 25% of the site area becoming
impervious, typically made up of roof and hardstand/road areas.
For the purposes of stormwater quality management, the following design
standards have been considered;
Table 3.4 – Desired Standard of Service – Stormwater Management
– Noosa Priority Infrastructure Plan
Table 14-61 – Water Sensitive Design Code – The Noosa Plan
Table 2 – Implementation Guideline No. 7 - South East Queensland
Regional Plan.
The proposed development will result in ≤ 25% of the site being covered by
impervious surfaces. In accordance with Item 3 – Table 2 – Design Objectives for
Urban Stormwater Management – Implementation Guideline No. 7 - SEQ Regional
Plan the development is exempt from pollutant load reduction targets provided;
Stormwater from all impervious areas is captured and managed prior to
discharge
Management of captured stormwater includes reuse of stormwater and
/or infiltration of stormwater to native soils.
______________________________________________________________________________
C5756/17/Engineering Report - 27 Attunga Heights, Noosa Heads 5
January 2017 JW/jl
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Attachment 4 - Engineering Report.pdfRelated documentApplication case desk ↗
About this file
- File size
- 18.7 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.