In order to comply with the above conditions, it is proposed to direct all roof
runoff to rainwater attenuation/reuse tanks. A 5kL rainwater detention tank will
be provided for each new dwelling (covenant requirement) for stormwater
attenuation as per the previous section, with a second tank with capacity of 3kL
provided for indoor non-potable and outdoor irrigation reuse.
Access driveway runoff will be directed to Rapid Infiltration Pits (RIP’s) for
minor event treatment, with major event overflow discharging via a stabilised
level spreader into the existing gully within the site.
Please refer to the attached preliminary engineering drawings for details and
locations of the proposed RIP’s.
An 1800mm diameter x 1700mm RIP is proposed to accept discharge from each
access driveway sub-catchment. Where required, pits will be linked by overflow
pipework which will discharge major storm event runoff to the existing
waterway via a stabilised level spreader.
Please refer to the attached engineering drawings in Appendix C for locations of
the rainwater tanks and rapid infiltration pits.
This approach is considered to satisfy the requirements of the above listed State
and Council guidelines.
7.0 SEWERAGE RETICULATION
Proposed units 1-12 will be connected to reticulated sewer via an internal gravity
sewer network than will connect to the existing manhole SM2668739 in Picture
Point Crescent with an Invert level of 19.35m AHD (from UW records).
Proposed Lot 2 can readily connect to existing manhole SM2670601 located just
outside of north-east boundary. Similarly, proposed Lot 3 can be serviced by the
existing manhole SM2670583 located in Alma Way.
It is proposed that Lot 4 be serviced by a privately owned packaged pump
station with macerator, which will lift effluent to the existing manhole in Alma
Way, SM2670588. Adjacent gravity reticulation is approximately 3-5m above
expected lot finished floor levels.
______________________________________________________________________________
C5756/17/Engineering Report - 27 Attunga Heights, Noosa Heads 6
January 2017 JW/jl
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Attachment 4 - Engineering Report.pdfRelated documentApplication case desk ↗
About this file
- File size
- 18.7 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.