Response to Further advice - 2023-01-11 RFI response · MCU22/0144
Vehicle Swept Paths
3. Provide additional Vehicle Swept Path Plans that demonstrate a B99 vehicle is
capable of entering the above Visitor Bays and Unit Carparks in a forward gear,
exit the space in a reverse gear and exit the site in a forward gear in a total of
3 movements without entering proposed landscaped areas or colliding with
features of the development (i.e. retaining walls). The additional plans must be
prepared by a suitably qualified person (RPEQ – Registered Professional
Engineer of Queensland).
The swept paths have been updated to ensure that the vehicle body does not pass
over landscaping areas nor retaining walls. Please refer to plans C60, C61 and C62.
Sustainable Building Design Code
4. Provide updated plans which incorporate rainwater collection and reuse at the
site, sufficient to supply external non-potable fixtures such as communal
landscape irrigation and bin washdown. The rainwater tanks should collect
roofwater only (not surface runoff) and be located within communal open
space areas of the site.
In accordance with the accepted outcome for the Sustainable Building Code, 3,000L
of rainwater reuse storage has been provided as a below ground storage tank,
nominally a Humes Rainvault RV3000-01-00 or equivalent. The maximum possible roof
area is to be directed to the tank, with downpipes fitted with first flush capture devices
to minimise pollutants being washed into the tank. The SWMP and design plans have
been updated to reflect this addition.
The rainwater reuse tank is to be plumbed to internal and external non-potable water
fixtures including external irrigation fixtures, internal toilets and laundry areas, and is
to be fitted with an automatic switching device to supply water when tank storage is
exhausted. Design of the roof drainage system and reuse pump and supply is to be
undertaken by the hydraulic consultant.
For further details on the other items of the information request, please refer to the town
planning response.
We believe that the above satisfactorily addresses the engineering matters raised in the
information request however, should additional information be required, please contact
our office directly.
Yours faithfully,
RECOR Pty Ltd
Prepared by
Ben Parry
Civil Engineer
BEng (Hons), MIEAust CPEng NER
RPEQ: 28084
P +61 7 5211 1003 A 75 Noosa Dr, Noosa Heads Qld 4567 E [email protected] recorconsulting.com
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Response to Further advice - 2023-01-11 RFI response.pdfRelated documentApplication case desk ↗
About this file
- File size
- 136 KB (small file)
- File type
No other editions are linked here.