Detailed design will also need to account for relevant factors of safety to maintain the temporary and
long-term stability of the retention system and control deflections so as not to put neighbouring
structures or underground services at risk or distress.
Retaining structures greater than 1 m high, or those required to support surcharge loads or sloping
backfill, will require engineer design and certification of construction. Retaining wall design should be
carried out in accordance with AS4678-2002 Earth retaining structures.
Design for temporary and permanent retaining structures could be carried out using a trapezoidal (for
propped or anchored walls) pressure distribution applicable to the wall type and based on the
parameters listed in Table 4. These values do not include allowance for hydrostatic pressures nor
transient (e.g. construction) or adjacent footing loadings.

Table 4: Retaining Structure Design Parameters

                               Unit                          Lateral earth pressure coefficients
                                              Friction
 Retained material             weight                        Ka                   Ko                    Kp
                                              angle (°)
                               (kN/m3)                       (Cantilever wall)    (Non-yielding wall)
                               18             28             0.36                 0.53                  2.77
 Very Loose/ Loose
 Sands


                               19             34             0.28                 0.44                  3.54
 Medium Dense (or
 Denser) Sands


                               *              *              *                    *                     *
 Future Controlled Fill*


Note:   * Depends on fill material type and level of compaction.

Retaining structures must be founded as per the recommendations in Section 6.3.2 above with the piled
footings, if required, also designed to resist lateral loads imposed by the retaining wall. Detailed design
must include an assessment of stability.


6.5          Drainage
Surface diversion drainage should be constructed above the crest of any new cut or fill embankment or
retaining walls (e.g. grassed or landscaped swales or diversion mounds). Adequate site drainage must be
installed to ensure that stormwater runoff is directed away from building walls, footings, batters and
retaining walls.
Although unlikely, if groundwater seepage is encountered during excavations, Tectonic must be notified
to assess the impact on stability.
All excess stormwater collected around the residence (including overflow from rainwater tanks etc.) must
be directed by pipes or lined channels to discharge into the existing stormwater infrastructure along
Bottlebrush Avenue or Noosa Drive. Subsurface disposal of stormwater must not be undertaken.



Proposed Unit Development
30 September 2024 | 24265-001-Rev0                                                                             16

Used in these records

About this file

File size
6.8 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Geotechnical Investigation.pdf · 6.8 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.