Delegated Report - Code - Planning OPW24 0180
2. The Currency Period for this development approval lapses if the development has not
substantially started by 15 November 2026, unless an application to extend the currency
period is approved by Council.
SITE SPECIFIC CONDITIONS
Bonds
3. A compliance bond of $5,000 is to be submitted to Council prior to the pre-start meeting. The
pre-start meeting will only be held once Council's Construction Engineering Officer has
confirmation that the bond monies have been received by Council.
The bond will be refunded less any costs incurred by Council in ensuring compliance with
these conditions or any additional inspections incurred for substandard work or work
undertaken not in accordance with this permit.
4. Bonds must:
a. have approval of the bond calculations and amount from Council prior to lodgement
b. be lodged with Council and accompanied by the Bond Administration Fee/s.
c. be requested for release by writing to Council, when relevant approval requirements
have been met.
Geotechnical Stability
5. All works must be carried out in accordance with a Geotechnical Report (or part thereof)
prepared by a qualified person*.
*(Refer to Advisory Note)
GENERAL CONDITIONS
Engineering
6. A condition report including photographs of the frontage of the site must be completed and
submitted to Council prior to the prestart meeting.
7. The principal contractor must have all the appropriate insurance and public liability
documentation to carry out the works. The principal contractor is also responsible to ensure
that any subcontractors also have the appropriate insurance and public liability
documentation. Certificates demonstrating currency of public liability insurance and works
insurance covering the works must be submitted to Council prior to the prestart meeting.
8. Council must be contacted at least 5 working days prior to any works commencing to
organise a prestart. The contact number to arrange a pre-start meeting is 5329 6245. The
pre-start meeting must include the relevant parties for the following aspects of the works:
a. Civil engineering works.
9. A Construction Management Plan must be submitted to Council prior to the pre-start meeting
and must specifically address the following:
a. traffic Management during the construction phase;
b. appropriate traffic signage in accordance with the Manual of Uniform Traffic Control
Devices (MUTCD); and
c. provision for safe pedestrian access across the frontage of the site both during and
outside working hours.
10. Any changes to the details associated with the supervising RPEQ or Principal Contractor
during construction, must be notified to council in writing within five business days of the
change occurring.
11. Any conflict between the development and an existing or proposed service must be referred
to the relevant service authority for determination prior to commencement of works.
Page 5 of 9
Document Set ID: 23342778
Version: 3, Version Date: 15/11/2024
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.