Appendix D- Engineering Assessment
23098 - ESA/2
Page 8
Refer to Appendix C for the NSC Existing Services Code, Appendix E for the Concept Services Plan,
and Appendix F for the Dial-Before-You-Dig Plans.
5.5 Water Reticulation
Information obtained from Unitywater’s ArcGIS Mapping, there is an existing 300mm diameter
Asbestos Cement water main traversing the northern verge of Pearl Street, south of the site. There
is also an existing 100mm diameter Asbestos Cement water main traversing the eastern verge of
Elm Street, west of the site.
It is proposed to decommission the existing service and meter assembly from Pearl Street and
upgrade the existing service and meter assembly from the water main within Elm Street to service
the proposed development.
There are two fire hydrants currently providing adequate fire hydrant coverage within the vicinity
of the site.
It is anticipated that the existing water infrastructure has sufficient capacity to service the
proposed development. However, this will be confirmed by Unitywater during detailed design.
Refer to Appendix C for the NSC Existing Services Code and NSC Fire services for common private
title code, Appendix E for the Concept Services Plan and Appendix F for the Dial-Before-You-Dig
Plans.
5.6 Stormwater
Refer to the separate Site Based Stormwater Management Plan (SBSMP) prepared by Morgan
Consulting Engineers for considerations to stormwater.
5.7 Electricity and Telecommunications
The site can be serviced by electricity at the following locations:
1. Overhead power lines situated along the southern verge of Pearl Street, south of the site.
2. Overhead power lines situated along the eastern and western verge of Elm Street, west of
the site.
The site can be serviced by telecommunications at the following locations:
1. Underground Telstra cables situated along the northern and southern verge of Pearl Street,
south of the site, and along the eastern verge of Elm Street, west of the site.
2. Underground NBN cables situated along northern and southern verge of Pearl Street, south
of the site, and along the eastern verge of Elm Street, west of the site.
Refer to Appendix F for the Dial-Before-You-Dig Plans.
5.8 Gas
There is no existing gas main within vicinity of the site.
Engineering Services Assessment
Proposed Townhouse Development at 5 Pearl Street, Cooroy
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.