response to excavation code
Infrastructure protection No acceptable outcome provided -
PO10
Earthworks and vehicular access do not
adversely impact on the capacity, operations
and maintenance of existing infrastructure.
Environmental protection No acceptable outcome provided -
PO11
Earthworks minimise any adverse impact
upon groundwater, watercourses,
drainage lines, wetlands, and
native vegetation.
Dams AO12.1 Not applicable - the proposed
PO12 Where the site is in the Rural zone— development does not relate to a dam.
Dam location and construction does
not impact upon neighbouring
properties or road reserves, in terms 1. the land has a slope of less than
of— 25% (1:4);
2. the earthworks including cut and
fill batters and retaining walls
1. hydrology; are setback a minimum of 50
2. alteration of existing overland flow metres from the property
paths and patterns; boundary; and
3. landslide or failure of dam wall; 3. the size of the lot is greater than
and 5 hectares.
4. effluent disposal areas.
AO12.2
Where the site is in the Rural
residential zone or the Rural zone and
the lot is less than 5 hectares:
1. the land has a slope of less than
1:6;
2. the earthworks including cut and
fill batters and retaining walls
are setback a minimum of 20
metres from the property
boundary; and
3. the dam work involves less than
500m³ of material.
AO12.3
For all other zones—
No acceptable outcome provided