                      Pedestrian and Bicycle Facilities
               28.    Pedestrian and bicycle facilities must be provided for the development. The works must be
                      undertaken generally in accordance with TOD Consulting’s plan 21617-SK200, Rev B
                      “Preliminary Design – General Arrangement” and in accordance with an Operational Works
                      approval and must include in particular:
                      a.      a 1.5 metre wide concrete footpath within the road verge for the entire length of the
                              site’s frontage to Natasha Avenue, alignment to be determined at operational works
                              stage, with consideration given to the existing native trees in the road reserve;
                      b.             a 1.5 metre wide concrete footpath within the road verge for the entire length of
                              the site’s frontage to Katharina Street.
                      Stormwater Drainage
               29.    The site must be provided with a stormwater drainage system connecting to a lawful point of
                      discharge. The works must be undertaken generally in accordance with TOD Consulting’s
                      plan 21617-SK200, Rev B “Preliminary Design – General Arrangement” and in accordance
                      with an Operational Works approval.
                      Services
               30.    Unless otherwise stipulated by telecommunications legislation at the time of construction, the
                      development must be provided with all necessary conduits, pits and pipes to accommodate
                      the future connection of optic fibre technology telecommunications.
               31.    Certification must be submitted to Council from all relevant service providers (Energex, NBN
                      and Unitywater) which certifies that the development has met the requirements of this
                      Decision Notice and all applicable legislation at the time of construction.
                      Easements
               32.    Unless otherwise agreed in writing by the relevant service provider, any public or third party
                      infrastructure located on the subject site must be placed within an easement registered
                      against the title of the property.
               33.    All easements must be designed in accordance with the planning scheme and granted at no
                      cost to the Grantee. Where the Grantee is Council or a service authority, the easement
                      documentation must be in accordance with the Grantee’s standard easement terms. Draft
                      easement documentation must be submitted to Council for endorsement.
               34.    All works must be kept clear of any existing or proposed easements on the subject land,
                      unless agreed otherwise in writing by the Grantee.
                      Earthworks and Retaining Walls
               35.    All excavation, fill and associated batters must be undertaken generally in accordance with
                      TOD Consulting’s plan 21617-SK100, Rev B “Preliminary Design – Earthworks” and in
                      accordance with an Operational Works approval, and contained entirely within the subject
                      site unless written permission from the respective landowner(s) is provided to Council.
               36.    All retaining walls must be designed and constructed in accordance with the planning scheme
                      and must be certified by an RPEQ where exceeding 1.0m in height. All retaining walls that
                      are publicly accessible and exceed 1.0m in height must be fitted with a commercial grade
                      safety fence.
                      Damage to Services and Assets
               37.    Any damage caused to existing services and assets as a result of the development works
                      must be repaired at no cost to the asset owner at the following times:
                      a.      where the damage would cause a hazard to pedestrian or vehicle safety, immediately;
                              or
                      b.      where otherwise, upon completion of the works associated with the development.




                                                                                                        Page 6 of 10
Document Set ID: 22091773
Version: 3, Version Date: 05/09/2022

Used in these records

About this file

File size
204 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

002 ECM_22091773_v3_Decision Notice - Approved by Delegation of Authority MCU21 0231.pdf · 204 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.