001 ECM_21885502_v3_Minor Change Existing Approval OPW21 0134 01 · OPW21/0134.02
Officer: Mark Lewis
Direct Telephone: 07 53296290
Our Reference: OPW21/0134.01
Your Reference: 17623 – 01/02/2022
12 April 2022
WAG INVESTMENTS
C/- Tod Consulting Pty Ltd
PO Box 61
NOOSAVILLE QLD 4566
[email protected]
Dear Sir,
Decision Notice – Minor Change
Planning Act 2016
I refer to your application received on 2 February 2022, requesting a minor change to an existing
development approval. Council decided your requested changes.
Details of the decision are as follows:
1. APPLICATION DETAILS
Application No: OPW21/0134.01
Street address: 135 Lake Weyba Dr Noosaville Qld 4566
Real property description: Lot 1 RP 36729
Planning Scheme: Noosa Plan 2020 (25 September 2020)
2. DECISION DETAILS
The following type of approval was issued on 27 October 2021.
Development Permit for Operational Work - Road work, Drainage work, Landscaping,
Electrical Reticulation, Stormwater, Earthworks, Clearing Veg
In relation to representations, Council on 2 December 2021 decided to:
A. Amend condition 1
B. Include additional 56
In relation to the request to make a minor change to the existing approval, Council on 11 April 2022,
decided to approve the requested changes. The changes are detailed below.
A. Approve the change.
B. Amend condition 1.
3. CURRENCY PERIOD OF APPROVAL
The currency period for this development approval is stated in the conditions below.
PO Box 141 P. (07) 5329 6500 [email protected]
TEWANTIN QLD 4565 F. (07) 5329 6501 www.noosa.qld.gov.au
Page 1 of 14
Document Set ID: 21885502
Version: 3, Version Date: 12/04/2022
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalFull text of the other 13 pages
Page 2
4. ASSESSMENT MANAGER CONDITIONS
APPROVED PLANS
1. Development undertaken in accordance with this approval must generally comply with the
approved plans of development. The approved plans are listed in the following table unless
otherwise amended by these conditions.
Plan No. Rev. Plan/Document Name Date
17623-C000 F Locality Plan, Drawing Index and Notes 17 March
as prepared by Tod Consulting 2022
17623-C001 F Plan of Development as prepared by Tod 17 March
Consulting 2022
17623-C100 F Earthworks, Erosion and Sediment 17 March
Control Plan as prepared by Tod 2022
Consulting as annotated by Council
17623-C200 F Roadworks and Drainage Plan as 17 March
prepared by Tod Consulting 2022
17623-C201 F Roadworks Details as prepared by Tod 17 March
Consulting 2022
AC1212-S4400232 1 A Electrical Reticulation as prepared by 27 July 2021
of 2 Auspower Connect
AC1212-S4400232 1 A Electrical Reticulation as prepared by 27 July 2021
of 2 Auspower Connect
AC1212- B NBN Pit and Pipe Design Stage 1 4 New 21 July 2021
CAD_REF_AC1212T Connections as prepared by Auspower
Connect
Report 19060 Final Bushfire Management Plan as prepared 03 June 2021
by Land and Environment Consultants
LAK07 B Vegetation Management Plan as September
prepared by Urban Forest Concepts 2021
CURRENCY PERIOD
2. The Currency Period for this development approval lapses if the development has not
substantially started by 03 November 2023, unless an application to extend the currency
period is approved by Council.
SITE SPECIFIC CONDITIONS
3. The Erosion and Sediment Control elements of Plan Number 17623-C100 have not been
approved. Erosion and Sediment Control Plans must be regularly revised and updated by a
suitably qualified person (CPESC or RPEQ with relevant experience) during development
works.
4. The existing crossover to the existing dwelling on proposed Lot 3 must be removed and the
verge area reinstated to match the existing verge treatments. Grassed verge areas to be
reinstated must be provided with 100 mm topsoil and grass seed or turf, and must be
maintained by the developer until established.
Page 2 of 14
Document Set ID: 21885502
Version: 3, Version Date: 12/04/2022
Page 3
PRIOR TO COMMENCEMENT OF WORKS
Tree Clearing/Retention
5. The Tree Survey/Civil Works Overlay plan from Appendix 6 of the approved Vegetation
Management Plan must be amended and submitted to Council for approval prior to the
prestart meeting with the amendments to include:
a. A colour coded legend included on the plan to be read in conjunction with the map; and
b. Corresponding colour coding included on the Tree Schedule table in Appendix 4 of the
approved Vegetation Management Plan.
6. Tree/vegetation protection fencing must be installed under the supervision of the Project
Arborist in accordance with the Vegetation Management Plan as prepared by Urban Forest
Concepts.
Engineering
7. Prior to the pre-start meeting, all necessary approvals from external service providers (e.g.
Unitywater, Energex, NBN) and external parties on which the development works are
proposed have been obtained and a copy supplied to Council.
8. A condition report including photographs of the frontage of the site and the section of Lake
Weyba Dr where the reconstruction works will tie into must be completed and submitted to
Council prior to the prestart meeting.
9. The principal contractor must have all the appropriate insurance and public liability
documentation to carry out the works. The principal contractor is also responsible to ensure
that any subcontractors also have the appropriate insurance and public liability
documentation. Certificates demonstrating currency of public liability insurance and works
insurance covering the works must be submitted to Council prior to the prestart meeting.
10. Council must be contacted at least 5 working days prior to any works commencing to
organise a prestart. The contact number to arrange a pre-start meeting is 5329 6500. The
pre-start meeting must include the relevant parties for the following aspects of the works:
a. Civil engineering works;
b. Tree protection/clearing works;
c. Electrical reticulation works;
d. Erosion and sediment control works; and
e. Other relevant parties.
11. A Construction Management Plan must be submitted to Council prior to the pre-start meeting
and must specifically address the following:
a. Traffic Management during all aspects of the construct phase including:
i. A Traffic Management Control Plan in accordance with Manual of Uniform Traffic
Control Devices (MUTCD) detailing all temporary signage and traffic control
measures prior to construction;
ii. Maintenance of safe pedestrian access across the frontage of the site both during
daily construction and after daily construction has ceased;
iii. Any proposed fencing to the site during the construction phase of the
development;
iv. No queuing of trucks is permitted on residential streets, especially prior to
7.00am. Further parked trucks must have engines turned off.
b. Maintenance and protection of water quality and existing drainage lines through the
construction site through the implementation of appropriate erosion and sediment
control measures;
Page 3 of 14
Document Set ID: 21885502
Version: 3, Version Date: 12/04/2022
Page 4
c. Works programme identifying key components of the works and their respective
durations;
d. Establishment of a communication protocol with the general public, adjoining owners,
emergency services and local businesses to advise of agreed construction times,
impacts on traffic and services and other relevant issues;
e. Include a post out to the local residents advising of the proposed development, the
expected time frames and the site contact details;
f. Include signage in prominent locations on the boundaries of the site advising of the
proposed development, the expected time frames and the site contact details; and
g. For haulage operations involving significant volumes of fill material or excavated
material being transported onto or off the site: details on the location of external fill
sites/sources, the haulage route, type of vehicle to be utilised during filling operations
and frequency of usage. NB any damage to the existing road system as a result of
haulage operations shall be fully repaired at the applicant’s expense.
12. Any changes to the details associated with the supervising RPEQ or Principal Contractor
during construction, must be notified to council in writing within five business days of the
change occurring.
13. Any conflict between the development and an existing or proposed service must be referred
to the relevant service authority for determination prior to commencement of works.
Bonds
14. A site control and/or compliance bond of $50,000 is to be submitted to Council prior to the
pre-start meeting. The pre-start meeting will only be held once Council's Construction
Engineering Officer has confirmation that the bond monies have been received by Council.
The bond will be refunded less any costs incurred by Council in ensuring compliance with
these conditions or any additional inspections incurred for substandard work or work
undertaken not in accordance with this permit.
DURING CONSTRUCTION
Engineering
15. All works must be supervised by a Registered Professional Engineer of Queensland (RPEQ)
who is independent of the Developer and Principal Contractor, and they must certify that all
works conform to the Operational Works permit. Where municipal works are involved, such
confirmation must be submitted for the respective hold points prior to any site inspection by
Council Officers.
16. All works must be constructed and work procedure undertaken in accordance with:
a. The approved plans/documents and conditions detailed in this Decision Notice;
a. The relevant conditions of the higher order Final Order No. 61 of 2018 for a
Reconfiguration of Lot viz. RAL21/0504 to which this approval relates;
b. All relevant Noosa Council Planning Scheme Policies, standard drawings, standard
specifications and guidelines; and
c. The latest version of the Healthy Waterways document “Water Sensitive Urban Design
Technical Design Guidelines for South East Queensland” for all water quality devices
to be constructed on site.
Roadworks (External Roadworks & Road Widening Works)
17. All pavement widening or construction of new pavement must join neatly to the existing
pavement so that there are no irregularities in line or level resulting at or adjacent to the join
for the length of the construction. Where necessary the existing pavement must be brought
to a satisfactory standard to allow for the above.
Page 4 of 14
Document Set ID: 21885502
Version: 3, Version Date: 12/04/2022
Page 5
18. All street surfacing must consist of a minimum depth of 30mm of an approved hot mixed
asphaltic concrete, unless other pavement types are approved as feature areas in
intersection thresholds, speed control devices, turning areas, indented parking etc.
19. The installation and/or modification of any traffic signs, street signs, line marking and Raised
Reflective Pavement Markings (RRPMs) must be in accordance with the Manual of Uniform
Traffic Control Devices (MUTCD). New or relocated signage must be installed using the VLok
installation system. All new signage must be Class 1 retroreflective material in accordance
with AS 1906.1, Retroreflective materials and devices for road traffic control purposes – Part
1: Retroreflective sheeting.
20. The developer must notify Council’s Traffic Engineer for any works involving the removal or
modification of existing Council traffic signs prior to such works commencing.
Pavement Design and Construction
21. The pavement design for the reconstruction of Lake Weyba Dr is not approved. To attain
approval for the pavement design, the following details must be submitted and certified by
an RPEQ with the proposed pavement design:
a. The design CBR must be based on the four day soaked CBR value for the subgrade
material;
b. The design subgrade CBR must be representative of each homogenous insitu section
of finished subgrade. With respect to each section:
i. For four or less test results, the design CBR must be taken as the least estimated
insitu CBR result.
ii. For five or more test results, the design CBR must be taken as the 10th percentile
of all estimated insitu CBR results.
c. The samples must be taken generally in the position of the outer wheel path on both
sides of the proposed road. A sketch plan showing the location of all tests must be
submitted with the test results for pavement design approval; and
d. Where imported material has been (or is proposed to be) used for subgrade
replacement, and the depth of the imported material is less than 300mm, the pavement
design CBR must be based on the testing results of the insitu material and not the
imported material.
22. At the time of subgrade inspection, the subgrade must exhibit no visible signs of deformation
under proof rolling by a fully loaded water truck. The pavement subgrade will not be passed
until this requirement has been achieved.
23. Pavement design for privately owned works must be undertaken in accordance with the
relevant standards. Structural integrity of the driveway and car park areas will remain the
responsibility of the property owner/developer and must be certified by an RPEQ.
Works within Road Reserve/Reinstatement
24. Safe pedestrian access on all streets in the vicinity of the development must be maintained
at all times. Should footpath/road closures be necessary to carry out construction works,
Council’s Engineering Officer must be notified prior to the proposed closure and all
requirements complied with.
25. All frontage works must match neatly with existing road and verge/footpath features.
Additional works beyond the frontage may be required to provide an acceptable transition to
existing road and verge/footpath profiles.
26. Electrical conduits or other services proposed to be installed within existing and proposed
road reserves under existing sealed carriageways, concrete pathways, concrete/sealed
driveways or significant vegetation must be installed by boring. Trenching is not permitted,
unless specifically approved by Council.
Page 5 of 14
Document Set ID: 21885502
Version: 3, Version Date: 12/04/2022
Page 6
Site Access and Driveways
27. The communal driveway crossover must be constructed in accordance with Council’s
Standard Drawing RS-056 & RS-056.1.
28. The following must be complied with during the construction of the required
crossover/driveway:
a. The driveway surfacing must consist of either an approved hot mixed asphaltic
concrete or patterned/plain concrete;
b. The driveway must be constructed so as not to concentrate stormwater runoff onto
neighbouring properties;
c. Underground service conduits for water supply, electricity and any other services must
be provided as part of the access driveway;
d. The property access must be located a minimum of 1m clear of existing power poles,
streetlights or other signage. The developer is responsible for any necessary relocation
of existing services to provide this clearance and must contact the relevant service
authorities and comply with their requirements in relation to these works.
Earthworks and Retaining Walls
29. All earthworks shall be undertaken in accordance with the provisions of AS 3798 Guidelines
on Earthworks for Commercial and Residential Development, with geotechnical testing
undertaken in accordance with Section 8 of the Standard, and to a minimum of ‘Level 1’ as
defined in Appendix B. Test results as required by AS 3798, and a certificate of quality and
uniformity of fill shall be provided by a RPEQ and submitted to Council prior to Council signing
the Plan of Survey.
30. Fall protection must be provided to retaining walls that are over 1m high.
31. Any retaining walls within the bushfire protection zone shown in Figure 6.1 of the approved
Bushfire Management Plan, must be constructed with non-combustible or fire resisting
materials in accordance with the Bushfire Management Plan.
32. Slope and batters are a maximum grade of:
a. 1 in 4 for grassed areas;
b. 1 in 3 for planted areas; and
c. 1 in 2 for combined structural engineering and planting solutions.
Stormwater Drainage
33. Appropriate scour protection must be provided at the outlet of all stormwater pipes including
temporary outlets.
34. Works associated with this permit must not adversely impact on the existing drainage
conditions on other properties (e.g. by blocking or interfering with natural overland flows).
35. The fill works undertaken must not result in any ponding of stormwater within the proposed
lot or on adjacent lots. Any reshaping works required to prevent ponding must be effectively
stabilised with turf or equivalent stabilisation method.
36. Construction of all internal stormwater drainage works must comply with the relevant
section/s of Australian Standard AS/NZS 3500.3.
Erosion and Sediment Control
37. Prescribed Water Contaminants (as defined in Schedule 10 of Environmental Protection
Regulation 2019) must not be released from the site or to waters within the site, or be likely
to be released should rainfall occur, unless all reasonable and practicable measures are
taken to prevent or minimise the release and concentration of contamination.
Page 6 of 14
Document Set ID: 21885502
Version: 3, Version Date: 12/04/2022
Page 7
38. Sediment and erosion control measures must be in place prior to works commencing. If such
measures are not in place or are not satisfactory, “on the spot” fines may be issued. Such
fines can be issued if sediments from the site are found to enter or have the potential to enter
Council’s stormwater system, natural waterways, any downstream stormwater filtration
system or adversely impacting on other properties. The sediment and erosion control design
and measures have NOT been approved, it is the site's Supervising Engineer who is
responsible for ensuring that the sediment and erosion control measures have:
a. Been duly designed by an RPEQ or CPESC and constructed in accordance with "best
practise" methods;
b. Been revised by an RPEQ or CPESC to address the issues raised by changes in the
projected construction schedule and/or methods;
c. Been revised to address predicted rainfall events; and
d. Achieve the desired environmental outcomes.
Council may request further controls to be installed should the implemented measures be
found inefficient.
39. The erosion and sediment control measures must be designed, installed and maintained in
accordance with the Supervising Engineer’s instructions and the current best practice
standards * (Refer to Advisory Note).
40. The developer must ensure non-essential exposure of soil is prevented by restricting the
extent of disturbance and minimising the duration of soil exposure to adverse weather
conditions and effectively turf, cover or stabilise any disturbed area without delay and prior
to rainfall occurring.
41. The developer must ensure sediment does not leave the site or enter onto adjoining
properties or Council’s drainage system due to surface runoff or on tyres of vehicles and/or
machinery. It is essential to implement appropriate approved erosion and sediment control
measures throughout the site during all phases of construction including vehicle shakedown
pad/grid (or similar) at the access to the construction site. Where sediments or other
contaminants are deposited on a road, they must be removed so as not to enter Council’s
drainage system or waterways.
42. Prior to the completion of the development and commencement of use, all site surfaces must
be effectively stabilised using methods which have achieved effective short-term stabilisation
and which will continue to achieve effective stabilisation in the medium to long-term. For the
purpose of this condition, an effectively stabilised surface is defined as one that does not, or
is not likely to result in visible evidence of soil loss caused by sheet, rill or gully erosion or
lead to sedimentation, or lead to water contamination.
43. A log book for the Erosion and Sediment Control measures and inspections must be
maintained by the site manager and made readily available to Council when requested. The
Supervising Engineer must verify and endorsed the E&SC measures upon their installation,
and periodically check these measures and the log book during construction and the
stabilisation stages. Any defects in erosion and sediment control devices, such as sediment
fences, are to be inspected and documented. Upon Inspection, the contractor is to determine
whether the device should be replaced or repaired. Documentation is to include how the
damage was caused and what measures can be implemented to reduce the possibility of
repeat occurrences. Any damage to either permanent or temporary water quality control
structures or devices is to be immediately rectified at the contractor’s expense.
The effectiveness of the erosion and sediment control devices must be monitored. All ESC
measures are to be inspected:
a. At least daily (when work is occurring on site) or weekly (when work is not occurring on
site); or
b. Within 24 hours of expected rain; or
Page 7 of 14
Document Set ID: 21885502
Version: 3, Version Date: 12/04/2022
Page 8
c. Within 18 hours of a rainfall event (i.e. an event of sufficient intensity and duration to
mobilise sediment on site).
Damage to Services and Assets
44. Any damage caused to existing services and assets as a result of the development works
must be repaired at no cost to the asset owner at the following times:
a. Where the damage would cause a hazard to pedestrian or vehicle safety, immediately;
or
b. Where otherwise, upon completion of the works associated with the development.
Any repair work which proposes to alter the alignment or level of existing services and assets
must first be referred to the relevant service authority for approval.
Vegetation Clearing/Retention
45. A qualified person* must be engaged for the duration of the works to:
a. Ensure works are carried out in accordance with the requirements of the approved
Vegetation Management Plan.
*(Refer to Advisory Note)
46. A QPWS recognised spotter-catcher must be engaged to manage fauna prior and during
clearing works in accordance with the requirements in the approved Vegetation Management
Plan and must:
a. Undertake pre-clearing inspections including fauna relocation and removal or blocking
of all vacant hollows;
b. Ensure clearing works avoids nesting times of animals and birds;
c. Co-ordinate staging and sequence of clearing with fauna protection;
d. Protect and recover fauna during clearing operations (not previously removed); and
e. Manage the translocation of animals and recovery procedures in accordance with
relevant legislation.
Street Trees
47. Inclusion of 1 Callistemon viminalis (or similar species approved by Council) public amenity
tree* within the road reserve for every 8 metres of road frontage to Lake Weyba Drive. These
street trees are not to be included in replacement plantings as required by the Vegetation
Management Plan.
48. Public amenity trees* must:
a. Meet Specifying Trees – a guide to assessment of tree quality (NATSPEC).
b. Minimum 45L pot size.
c. Meet landscaping requirements detailed within Noosa Plan 2020 – PSP2 Landscaping.
d. Be located in accordance with engineering requirements for safe vehicle and
pedestrian sight lines.
e. Be located on the roadside side of the power lines.
f. Be located from services and infrastructure a minimum of:
i. 6m from electricity poles and pillars.
ii. 4m from street lighting.
iii. 2m from stormwater catchment pits.
iv. 2m from any adjoining driveway.
Page 8 of 14
Document Set ID: 21885502
Version: 3, Version Date: 12/04/2022
Page 9
g. Ensure mulch is placed around each tree, comprising of leaf and limb material of
varying sizes, free of foreign matter including anthropogenic waste, rock, soil/sediment
contamination and is applied to all planting areas to ensure a minimum 100mm depth
once settled.
*(Refer to Advisory Note)
Weed Management
49. Weed control and management works must be undertaken in accordance with the approved
Vegetation Management Plan including the ongoing management of Singapore Daisy.
Bushfire Management
50. All works must be undertaken in accordance with the relevant requirements of the approved
Bushfire Management Plan.
FOLLOWING CONSTRUCTION / PRIOR TO COUNCIL SIGNING THE PLAN OF SURVEY
Certification
51. Upon completion of the work and prior to signing the plan of survey, the following
certifications must be provided to Council:
a. A certificate issued by an RPEQ certifying that the works have been constructed in
accordance with the Operational Works permit and the requirements of the Bushfire
Management Plan.
b. A certificate issued by the Project Arborist certifying that the works have been
undertaken in accordance with this approval and the requirements of the approved
Vegetation Management Plan.
As Constructed Plans and ADAC XML Files (Council)
52. Prior to acceptance of civil works to become Council assets “On Maintenance”, satisfactory
“As-Constructed” records must be submitted to Council. The bundle of “As Constructed”
information shall include:
a. As-Constructed Engineering Drawings. Data is to be submitted in an electronic drawing
file format (.dwg), with all plans clearly endorsed “As-Constructed”, along with the
accompanying hardcopies (PDFs of the As-Constructed .dwg drawing files), and;
b. ADAC XML Digital File. ADAC File format (ADAC - Asset Design As Constructed)
prepared in accordance with industry standards and recorded in “MGA - UTM56 /
GDA94” projection.
Please Note: Further information and advice relating to the as-constructed drawing
presentation, as-constructed survey capture and associated guidelines for preparation
of a compliant ADAC XML digital file are available on the webpage titled “As-
Constructed Guidelines” and accessible at the Noosa Council Website: Planning &
Development / Development Tools & Guidelines / As-Constructed Guidelines.
c. The “As-Constructed” drawings will require certification by a:
i. Qualified experienced Civil Engineer (RPEQ) confirming design intent and
conformance with applicable standards and specifications, along with the
relevant descriptions of assets, services and structures and;
ii. Licensed Surveyor in regard to the cadastral and locational information, levels
and applicable survey datum.
d. The data must be in accordance with Council’s “Planning Scheme Policy 6 –
Engineering Design Standards”, and fully detail the levels for all engineering works
including but not limited to the drainage network and structures, finished ground and
pavement surface levels.
Page 9 of 14
Document Set ID: 21885502
Version: 3, Version Date: 12/04/2022
Page 10
e. Landscaping, including all assets and improvements within parks, open space and road
reserves areas are to be shown on an accompanying separate landscape plan
(prepared in .dwg file format with accompanying hardcopy PDFs) and include a
complaint ADAC XML file. Details of the landscaping and all associated assets and
improvements may be included in the ADAC XML digital file prepared for associated
civil infrastructure, or alternatively, be provided as a separate ADAC XML digital file
containing landscape and asset information only.
f. The building envelope data must be submitted in both hardcopy and digital format
(ADAC XML Digital File). ADAC - Asset Design As Constructed, is to be prepared in
accordance with industry standards and recorded in “MGA - UTM56 / GDA94”
projection.
On Maintenance
53. All municipal works must be accepted ‘On Maintenance’ by Council in accordance with
Council’s relevant Planning Scheme Policy prior to plan sealing. To achieve ‘On
Maintenance’, the supervising RPEQ must submit to Council:
a. Certification that all works have been undertaken and completed in accordance with
the requirements of this Permit;
b. As Constructed details in accordance with Council’s Planning Scheme Policy; and
c. Maintenance and operational manuals for all proprietary or site specific devices.
Off Maintenance
54. Prior to requesting an Off Maintenance inspection the developer must provide a written
request for the Off Maintenance inspection.
55. A re-inspection fee in accordance with Council’s Fees and Charge Register will be charged
where:
a. A Council inspection reveals works do not comply with approval requirements;
b. Submitted certification falsely states works comply with approval requirements.
ADDITIONAL CONDITION – 2 December 2021
56. Prior to the prestart meeting, provide a written agreement between the Developer and the
property owner(s) of No. 133 Lake Weyba Dr in regard to the potential impacts to their
frontage and crossover resulting from the construction of the necessary electrical
infrastructure. The agreement must address the extent of the reinstatement works and a copy
of the co-signed agreement must be submitted to Council.
5. REFERRAL AGENCIES
Not applicable.
6. ADVISORY NOTES
The following notes are included for guidance and information purposes only and do not form part
of the assessment manager conditions:
General Advisory Notes
1. As this driveway is a private structure, the owner bears full responsibly for the standard of its
construction, maintenance and any liabilities associated with its construction.
2. Council has undertaken an audit check of the Operational Works drawings in relations to the
proposed works. A detailed check of the calculations and drawings has not been undertaken,
as they have been certified by a RPEQ. The RPEQ bears full responsibility for all aspects of
the engineering design. Council reserves the right to require further amendments and/or
additions at a later date should design errors become apparent.
Page 10 of 14
Document Set ID: 21885502
Version: 3, Version Date: 12/04/2022
Page 11
3. Council reserves the right to call up any performance bond held or levy charges against the
property, should emergency works be required to be undertaken by Council to make the site
safe due to inactivity on the development site for extended periods of time.
4. Should any changes or modifications to the approved plans be required as a result of
construction constraints, a “Request to change an existing approval” under the Planning Act
2016 must be made. Amended plans clearly indicating the changes must be lodged with this
application along with the appropriate fees.
Prestart, On and Off Maintenance Inspections Request
5. Contact Council on 5329 6500 to arrange a prestart or an inspection giving a minimum of 5
business days’ notice of preferred inspection time.
6. If Council officers are required to undertake additional inspections of the same works, a
reinspection fee will be applicable in accordance with Council’s Fees and Charges register
applicable at the time.
7. A minimum maintenance period of 12 months will apply to all municipal works and thereafter
until such time as the works are performing in accordance with the approved design unless
noted otherwise
Environmental Advisory Notes
8. The Environmental Protection Act 1994 states that a person must not carry out any activity
that causes, or is likely to cause, environmental harm unless the person takes all reasonable
and practicable measures to prevent or minimise the harm. Environmental harm includes
environmental nuisance. In this regard persons and entities, involved in the civil, earthworks,
construction and landscaping phases of this development are to adhere to their ‘general
environmental duty’ to minimise the risk of causing environmental harm.
Erosion and Sediment Control
9. Accepted best practice standards include International Erosion Control Association
Australasia Best Practice Erosion and Sediment Control
10. Qualified Person, for the purpose of erosion and sediment control is a Certified Professional
in Erosion and Sediment Control (CPESC) or suitably experienced Registered Professional
Engineer of Queensland (RPEQ).
11. As a general rule, a site is determined to have achieved effective short-term stabilisation if
at the time of the plan sealing inspection:
a. Methods of stabilisation are:
Appropriate for slopes and slope lengths; and
Are consistent with best practice environmental management practices such as
in the Manual for Erosion and Sediment Control or the IECA Manual; and
b. Stormwater runoff from the site is not currently, and is not likely to result in visible
evidence of sedimentation or erosion, or lead to water contamination.
If at the time of request for plan sealing, the method of short-term stabilisation has not
achieved a level of stability that Council's Officers believe will have a high probability
of achieving long term stability (i.e. until house construction has occurred on all lots),
Council Officers may take the following matters into consideration in determining
whether the site is capable of achieving medium to long-term stability:
Evidence that the site has been effectively stabilised in the short term;
Evidence that soil has been adequately ameliorated;
Evidence that seed of annual and perennial grass species has been applied at
an adequate rate; and
Page 11 of 14
Document Set ID: 21885502
Version: 3, Version Date: 12/04/2022
Page 12
That grass seed has germinated at a density that is likely to achieve an effective
grass cover.
Vegetation Clearing/Retention
12. Qualified Person, for the purpose of:
a. Undertaking, supervising tree works and preparing arboriculture certification, is
considered to be a person with a minimum three years current experience in tree
protection, hazard identification/mitigation and Specifying Trees – a guide to
assessment of tree quality (NATSPEC) assessment and either:
i. International Society of Arboriculture (ISA) certification; or
ii. A Diploma of Arboriculture.
b. Managing Fauna protection is considered to be a certified Fauna Spotter Catcher
13. Public amenity trees are defined as any tree located within public streets, parks or areas that
will become publicly owned as a result of this development.
Infrastructure Charges
14. All developments and/or changes to existing developments may require payment of
“Infrastructure Charges” (as applicable) in accordance with Council’s “Charges Resolution”
made pursuant to the planning legislation and regulations current at the time of issue.
7. PROPERTY NOTES
The following property notes will be placed against the subject properties as specified in Council’s
property record system:
Flood Emergency Management Plan
“Lots 1, 2, 3 and 4 are all subject to a flooding hazard with a Flood Emergency Management Plan
(FEMP), as prepared by Water Technology 27 February 2020, in place for the lots. All owners and
occupiers of Lots 1-4, including successive landowners, are to be provided with a copy of the FEMP
which is to be implemented by the Body Corporate and landowners/occupiers.”
Bushfire Management Plan
“There is a Bushfire Management Plan (BMP), as prepared by Land and Environmental
Consultants 03 June 2021, in place that effects Lots 1, 2, 3 and 4. Prospective purchasers, property
owners and occupiers are to be provided with a copy of the BMP and are to ensure the Bushfire
Mitigation Plan detailed in the BMP is adhered to.”
Vegetation Management Plan
“For proposed lot 1, there is a requirement in the Vegetation Management Plan, that any boundary
fencing to the premises must allow the passage of native fauna.”
8. VARIATION APPROVAL DETAILS
Not applicable.
9. FURTHER DEVELOPMENT PERMITS REQUIRED
Not applicable.
10. SUBMISSIONS
Not applicable.
11. RIGHTS OF APPEAL
You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the
Planning Act 2016 is attached.
Page 12 of 14
Document Set ID: 21885502
Version: 3, Version Date: 12/04/2022
Page 13
During the appeal period, you as the applicant may suspend your appeal period and make written
representations to Council about the conditions contained within the development approval. If
Council agrees or agrees in part with the representations, a negotiated decision notice will be
issued. Only one negotiated decision notice may be given.
12. OTHER DETAILS
If you wish to obtain more information about the decision, electronic copies are available on line at
www.noosa.qld.gov.au or at Council Offices.
Yours faithfully,
Mark Lewis
Coordinator - Engineering
Enc: Appeal Rights
Approved Plans/Documents
cc. Unitywater
DECISION NOTICE HISTORY
Original Decision Notice – 27 November 2021.
Negotiated Decision Notice – 2 December 2021, with an amendment to condition 1 and include additional condition 56 .
Decision Notice - Minor - OPW21/0134.01 – 1 April 2022, with an amendment to condition 1.
Page 13 of 14
Document Set ID: 21885502
Version: 3, Version Date: 12/04/2022
Page 14
Appeal Rights
PLANNING ACT 2016 & PLANNING REGULATION 2017
Chapter 6 Dispute resolution (3) The appellant or, for an appeal to a tribunal, the registrar must,
within the service period, give a copy of the notice of appeal to –
Part 1 Appeal rights
(a) the respondent for the appeal; and
229 Appeals to tribunal or P&E Court
(b) each co-respondent for the appeal; and
(1) Schedule 1 of the Planning Act 2016 states –
(c) for an appeal about a development application under schedule
(a) Matters that may be appealed to –
1, table 1, item 1 – each principal submitter for the
(i) either a tribunal or the P&E Court; or development application; and
(ii) only a tribunal; or (d) for and appeal about a change application under schedule 1,
table 1, item 2 – each principal submitter for the change
(iii) only the P&E Court; and
application; and
(b) The person-
(e) each person who may elect to become a co-respondent for the
(i) who may appeal a matter (the appellant); and appeal, other than an eligible submitter who is not a principal
submitter in an appeal under paragraph (c) or (d); and
(ii) who is a respondent in an appeal of the matter; and
(f) for an appeal to the P&E Court – the chief executive; and
(iii) who is a co-respondent in an appeal of the matter; and
(g) for an appeal to a tribunal under another Act – any other
(iv) who may elect to be a co-respondent in an appeal of the
person who the registrar considers appropriate.
matter.
(4) The service period is –
(2) An appellant may start an appeal within the appeal period.
(a) if a submitter or advice agency started the appeal in the P&E
(3) The appeal period is –
Court – 2 business days after the appeal has started; or
(a) for an appeal by a building advisory agency – 10 business
(b) otherwise – 10 business days after the appeal is started.
days after a decision notice for the decision is given to the
agency; or (5) A notice of appeal given to a person who may elect to be a co-
respondent must state the effect of subsection (6).
(b) for an appeal against a deemed refusal – at any time after the
deemed refusal happens; or (6) A person elects to be a co-respondent by filing a notice of election,
in the approved form, within 10 business days after the notice of
(c) for an appeal against a decision of the Minister, under chapter
appeal is given to the person.
7, part 4, to register premises or to renew the registration of
premises – 20 business days after a notice us published under 231 Other appeals
section 269(3)(a) or (4); or
(1) Subject to this chapter, schedule 1 and the P&E Court Act, unless
(d) for an appeal against an infrastructure charges notice – 20 the Supreme Court decides a decision or other matter under this
business days after the infrastructure charges notice is given Act is affected by jurisdictional error, the decision or matter is non-
to the person; or appealable.
(e) for an appeal about a deemed approval of a development (2) The Judicial Review Act 1991, part 5 applies to the decision or
application for which a decision notice has not been given – matter to the extent it is affected by jurisdictional error.
30 business days after the applicant gives the deemed
(3) A person who, but for subsection (1) could have made an
approval notice to the assessment manager; or
application under the Judicial Review Act 1991 in relation to the
(f) for any other appeal – 20 business days after a notice of the decision or matter, may apply under part 4 of that Act for a
decision for the matter, including an enforcement notice, is statement of reasons in relation to the decision or matter.
given to the person.
(4) In this section –
Note – decision includes-
See the P&E Court Act for the court’s power to extend the appeal
(a) conduct engaged in for the purpose of making a decision; and
period.
(b) other conduct that relates to the making of a decision; and
(4) Each respondent and co-respondent for an appeal may be heard
in the appeal. (c) the making of a decision or failure to make a decision; and
(5) If an appeal is only about a referral agency’s response, the (d) a purported decision; and
assessment manager may apply to the tribunal or P&E Court to
(e) a deemed refusal.
withdraw from the appeal.
non-appealable, for a decision or matter, means the decision or
(6) To remove any doubt. It is declared that an appeal against an
matter-
infrastructure charges notice must not be about-
(a) is final and conclusive; and
(a) the adopted charge itself; or
(b) may not be challenged, appealed against, reviewed, quashed,
(b) for a decision about an offset or refund-
set aside or called into question in any other way under the
(i) the establishment cost of trunk infrastructure identified in Judicial Review Act 1991 or otherwise, whether by the
a LGIP; or Supreme Court, another court, a tribunal or another entity; and
(ii) the cost of infrastructure decided using the method (c) is not subject to any declaratory, injunctive or other order of
included in the local government’s charges resolution. the Supreme Court, another court, a tribunal or another entity
on any ground.
230 Notice of appeal
232 Rules of the P&E Court
(1) An appellant starts an appeal by lodging, with the registrar of the
tribunal or P&E Court, a notice of appeal that- (1) A person who is appealing to the P&E Court must comply with the
rules of the court that apply to the appeal.
(a) is in the approved form; and
(b) succinctly states the grounds of the appeal. (2) However, the P&E Court may hear and decide an appeal even if
the person has not complied with the rules of the P&E Court
(2) The notice of appeal must be accompanied by the required fee.
Page 14 of 14
Document Set ID: 21885502
Version: 3, Version Date: 12/04/2022
Used in these records