Council archive · source document
001 ECM_21885502_v3_Minor Change Existing Approval OPW21 0134 01 · OPW21/0134.02
4. ASSESSMENT MANAGER CONDITIONS
APPROVED PLANS
1. Development undertaken in accordance with this approval must generally comply with the
approved plans of development. The approved plans are listed in the following table unless
otherwise amended by these conditions.
Plan No. Rev. Plan/Document Name Date
17623-C000 F Locality Plan, Drawing Index and Notes 17 March
as prepared by Tod Consulting 2022
17623-C001 F Plan of Development as prepared by Tod 17 March
Consulting 2022
17623-C100 F Earthworks, Erosion and Sediment 17 March
Control Plan as prepared by Tod 2022
Consulting as annotated by Council
17623-C200 F Roadworks and Drainage Plan as 17 March
prepared by Tod Consulting 2022
17623-C201 F Roadworks Details as prepared by Tod 17 March
Consulting 2022
AC1212-S4400232 1 A Electrical Reticulation as prepared by 27 July 2021
of 2 Auspower Connect
AC1212-S4400232 1 A Electrical Reticulation as prepared by 27 July 2021
of 2 Auspower Connect
AC1212- B NBN Pit and Pipe Design Stage 1 4 New 21 July 2021
CAD_REF_AC1212T Connections as prepared by Auspower
Connect
Report 19060 Final Bushfire Management Plan as prepared 03 June 2021
by Land and Environment Consultants
LAK07 B Vegetation Management Plan as September
prepared by Urban Forest Concepts 2021
CURRENCY PERIOD
2. The Currency Period for this development approval lapses if the development has not
substantially started by 03 November 2023, unless an application to extend the currency
period is approved by Council.
SITE SPECIFIC CONDITIONS
3. The Erosion and Sediment Control elements of Plan Number 17623-C100 have not been
approved. Erosion and Sediment Control Plans must be regularly revised and updated by a
suitably qualified person (CPESC or RPEQ with relevant experience) during development
works.
4. The existing crossover to the existing dwelling on proposed Lot 3 must be removed and the
verge area reinstated to match the existing verge treatments. Grassed verge areas to be
reinstated must be provided with 100 mm topsoil and grass seed or turf, and must be
maintained by the developer until established.
Page 2 of 14
Document Set ID: 21885502
Version: 3, Version Date: 12/04/2022
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
001 ECM_21885502_v3_Minor Change Existing Approval OPW21 0134 01.pdfRelated documentApplication case desk ↗
About this file
- File size
- 222 KB (small file)
- File type
No other editions are linked here.