                                                                              Traffic Management Plan


determination of appropriate measures to mitigate those risks. The process is appropriate at all levels of planning
and operation.

The process is carried out by first identifying all hazards likely to arise, evaluating them in terms of likelihood of
occurrence and adverse consequences using historical data, experience or other means. The proposed
procedural statement or traffic guidance scheme should ensure that adequate means of controlling or reducing
those risks found to be significant, are in place.

All traffic control guidance schemes will be designed, developed and implemented in accordance with the
MUTCD. Whilst it is considered that speeding through the traffic controlled work site posing a safety risk to the
controllers and or workers a speed management plan will be developed if such issues occur. This plan will
implement additions to the traffic guidance schemes through implementation of additional signage, advanced
warning signs and speed activated radars.

A Project Risk Register will be maintained by Shadforth and will be updated throughout the duration of the
construction activities or when works change. Additional risks will be assessed, and control measures
implemented as they are identified.

It is expected that the Engineer will provide a project Risk Assessment of the construction activities.




IMS-04-05_D - Reviewed May 2019                  Document Uncontrolled When Printed                        Page 21 of 30
Log in to download the original file

Traffic Management Plan_IMS-04-05_D (001) FOR APPROVAL.pdf · 1.1 MB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.