Traffic Management Plan_IMS-04-05_D (001) FOR APPROVAL

of 30

Page text shows just the words. Original shows the document exactly as it was published.

Plans and drawings

This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).

Log in to see the plans as drawn
                                                                              Traffic Management Plan


9.3 Traffic Controllers General Duties (if required)

A Traffic Controller is defined as:

A person who holds an appointment as an accredited person under Section 21 of the Transport Operations
(Road Use Management) Act 1995 to perform the functions of a traffic controller as prescribed by the Transport
Operations (Road Use Management - Accreditation and Other Provisions) Regulation.

All Traffic Controllers are to be trained and accredited with the QLD Traffic Controller Accreditation
Scheme and hold a QLD Construction White / Blue Card.

Traffic Controllers will set out and maintain signage as per the relevant TGS in accordance with MUTCD, and
traffic control shall be conducted as per the Approved Procedure for Controlling Traffic. Any personnel to
implement signage will be appropriately qualified as prescribed by the MUTCD. All Traffic Controllers will be
relieved of their duty after not more than 2 hours for a period of rest or other duties of at least 15 minutes.

It is the responsibility of the and onsite foreman / supervisor to monitor queue lengths and delay times caused
to the public. The maximum time any direction of traffic that will be held is <5mins, this will be communicated to
the work force at daily pre starts. This scope of works will plan to mitigate the impact on the road user by
choosing to select a preferable shoulder closure where possible, therefore still maintaining existing traffic lanes
configurations.



9.4 Traffic Control Devices

Certain traffic control signs are only to be displayed for specific work activities, this includes:

The Traffic Controller’s responsibility to ensure that signs are erected at the start of each day, and removed (or
covered) at the end of the day. It is not acceptable to keep these signs displayed if there are no works and
especially not overnight or outside work hours.

Traffic control and advance warning signs will be placed upon all approaches to the work site. Refer to Appendix
6 for details of placement of traffic management devices and after care signage.



9.5 Unplanned Oversize Vehicle Access

Although considered low risk for this project, Should oversized vehicles require access through the work zone
the following protocols will be followed. Traffic Controllers will may obtain positive communication over the UHF
channel 40 prior to the oversized vehicle approaching the area: Width and vertical clearance will be
communicate by any pilot vehicles. Based on the advanced warning, should the works site contain a single lane
closure that is restricting the required clearance for the oversized vehicle to pass through then this will be
communicated to the onsite foreman. Depending on the traffic control devices in place [likely single lane closure
/ hats/bollards] then all personnel, plant and equipment will be removed from the work site to a safe distance off
the carriageway. Traffic controllers will still remain in position controlling 2 way traffic under stop go conditions.
Upon the oversized vehicle manoeuvring through the work site, the bollards/hats will be removed by the traffic
controllers and reinstated following its passing – all other public vehicles will remain on stop until the traffic
control devices are reinstated (<5mins).




10. Risk Assessment
Risk management entails the identification and analysis of risks likely to arise during works on road including
the setting up, operating, changing and ultimate dismantling of a traffic guidance scheme, followed by the



IMS-04-05_D - Reviewed May 2019                  Document Uncontrolled When Printed                        Page 20 of 30
Log in to download the original file

Traffic Management Plan_IMS-04-05_D (001) FOR APPROVAL.pdf · 1.1 MB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.