Traffic Management Plan_IMS-04-05_D (001) FOR APPROVAL
Plans and drawings
This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).
Log in to see the plans as drawn Traffic Management Plan
▪ Greater difficulty to manage road users through works.
Advantages:
▪ Reduced delays at these sections of works.
Traffic past the Close one lane of traffic and operate under shuttle flow via the use of Option Adopted
worksite portable traffic signals.
Disadvantages:
▪ Impact to road users.
▪ Delays to road users
▪ Traffic controllers having to stop heavy vehicles
Advantages:
▪ Allows for road users to pass the works safely without risk of injury
or damage.
▪ Speed reduced to 40km/hr due to lane proximity to workers and
plant, thus reducing rick of workers being struck by vehicles.
Lateral Shift Lateral shift both lanes of traffic onto one lane and use unsealed Not Practical
shoulder as second lane.
Disadvantages:
▪ Insufficient space to allow for 2 x 3.5m lanes of sealed pavement
Advantages:
▪ This will allow access to unimpeded access to the work area for
resealing works to be completed.
▪ Less delays for road users.
▪ Positive customer experience.
IMS-04-05_D - Reviewed May 2019 Document Uncontrolled When Printed Page 29 of 30