Traffic Management Plan_IMS-04-05_D (001) FOR APPROVAL

of 30

Page text shows just the words. Original shows the document exactly as it was published.

Plans and drawings

This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).

Log in to see the plans as drawn
                                                                           Traffic Management Plan


This TMP developed by Shadforth considers the physical traffic and transport impact of the works on all road
users (not limited to but including cars, pedestrians, cyclists and public transport). This TMP is based on the
information contained in the contract documents, construction methods, program and site visits by the Traffic
Management Designer

If any part of the program or methods changes, it may be necessary for the TMP (and TGS’s) to be amended.



1.7 Document Structure



             DTMR                                                                               Stakeholder Expectations
     Standard Specification
      Provision for Traffic

                                                                                                      Traffic Data

            MUTCD
                                             TRAFFIC MANAGEMENT
                                              PLAN FOR PROJECT




                                                                                   Aftercare Plans
            TRUM                                                                    as Required




                                                Traffic Guidance
                                                    Schemes
      Road Planning and
        Design Manual




1.8 Distribution

Shadforth will develop and submit the TMP to the Contract Superintendent or Principals Representative.

It is intended that the TMP and the site-specific Traffic Guidance Schemes (TGS’s) will be continually updated
and amended, as required, during the contract period in response to any incidents, consultation/ meetings with
work force, traffic disruptions, audits or changes in the design and construction process.

1.9 Site Specific Traffic Guidance Schemes

TGS’s will be prepared for every scenario effecting relevant stakeholders necessary to complete the works.
These documents can be located in the appendices of this document.

The TGS’s will include detailed drawings that show proposed temporary signing and other traffic control device
layouts. The TGS’s will include details of:

▪    Lane or part road closures
▪    Major traffic control devices
▪    Approach speed / speed through works / departure speed
▪    Work site barrier locations
▪    Pedestrian and cyclist provisions
▪    Public transport provisions



IMS-04-05_D - Reviewed May 2019               Document Uncontrolled When Printed                                     Page 6 of 30
Log in to download the original file

Traffic Management Plan_IMS-04-05_D (001) FOR APPROVAL.pdf · 1.1 MB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.