ORDINARY MEETING AGENDA                                                           18 AUGUST 2022


    58.   All stormwater quality treatment devices must be maintained in accordance with the
          Water by Design (2009) Maintaining Vegetated Stormwater Assets (Version 1). The
          approved Operational Works drawings for the stormwater quality treatment system and
          detailed life cycle costing of the system must be attached as an addendum to this
          document. Records of all maintenance activities undertaken must be kept and made
          available to Council upon request.
    59.   Any proposed Community Management Statement required for the development must
          include Water by Design (2009) Maintaining Vegetated Stormwater Assets (Version 1)
          and must include the full cost of maintaining the system in accordance with Water by
          Design (2009) Maintaining Vegetated Stormwater Assets (Version 1). The cost of
          maintaining the system must be included in the proposed levies for each unit owner.
          Stormwater Drainage
    60.   The site must be provided with a stormwater drainage system connecting to a lawful
          point of discharge. The works must be undertaken in accordance with an Operational
          Works approval and the Queensland Urban Drainage Manual, and must include in
          particular:
          a.   the detention system generally as described in Stormwater Management Plan,
               prepared by MPN Consulting, dated 27th June 2022;
          b.   the use of gravity stormwater drainage and not surcharge pits to the maximum
               extent practicable. Surcharge pits may only be used where the catchment is
               composed of roof surfaces only;
          c.   provision of rainwater tanks for the capture and reuse of roof water for the irrigation
               of communal landscaping; and
          d.   accommodation for both severe storms or severe blockage of the underground
               drainage network. A Severe Storm/Severe Blockage Assessment for the drainage
               system proposed for the site is to be provided with the development application for
               operational works, and is to demonstrate that finished floor levels will not be
               inundated under either a severe blockage of the underground drainage network in
               the 1%AEP event at year 2100, or for a severe storm exceeding the 1%AEP based
               on design blockage.
          Acid Sulfate Soils
    61.   An Acid Sulfate Soil Management Plan must be prepared and submitted with the
          Operational Works application for the site. The acid sulfate management plan must
          include testing, monitoring and treatment requirements for the works.
          Services
    62.   Unless otherwise stipulated by telecommunications legislation at the time of
          construction, the development must be provided with all necessary conduits, pits and
          pipes to accommodate the future connection of optic fibre technology
          telecommunications.
    63.   Certification must be submitted to Council from all relevant service providers (Energex,
          NBN and Unitywater which certifies that the development has met the requirements of
          this Decision Notice and all applicable legislation at the time of construction.
          Easements
    64.   Unless otherwise agreed in writing by the relevant service provider, any public or third
          party infrastructure located on the subject site must be placed within an easement
          registered against the title of the property.




                                                                                      Page 25 of 55
Log in to download the original file

2022-08-18 Ordinary Meeting Agenda(PDF, 4MB).pdf · 4.7 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.