23. When requested by Council, a Noise Impact Assessment Report (NIAR) showing
monitoring and recording of noise levels must be undertaken to investigate any
complaint (other than a frivolous or vexatious complaint) caused by noise emissions
from operations at the premises. Such monitoring must be undertaken within a
reasonable and practicable timeframe nominated by Council and be performed by a
suitably qualified person in accordance with accepted guidelines and standards. The
report must be submitted to Council detailing the results of such monitoring and
recommendations for any measures to achieve compliance with limits outlined in
Table 1 of this Decision Notice.
For the purpose of measuring and certifying relevant noise conditions and reporting
(e.g. mechanical plant and equipment, a/c units, motors, refrigeration equipment,
compressors, pumps, rooftop plant and equipment. etc) a suitably qualified person is
either:
i) a Registered Professional Engineer of Queensland, or
ii) an environmental consultant with a minimum of three (3) years current
experience in the field of acoustics.
Public Health Act 2005 - Rainwater Tanks
24. In accordance with the Public Health Act 2005, rainwater tanks must be constructed
with mosquito proof screens (made from either brass, copper, aluminium or stainless
steel), and constructed with a mesh size of no more than 1mm, and must be installed
in a way that does not accelerate corrosion. Tanks that contain flap valves must be
installed so that when closed, mosquitoes cannot pass through the valve. It is
unlawful under the Public Health Act 2005 to construct, install or be in possession of
a tank that does not comply with these requirements.
25. Where it is intended to use rainwater for drinking purposes, a suitable treatment
system is required to be installed to disinfect or treat the water to microbiological and
physical standards as described in the current Australian Drinking Water Guidelines
2011 to make it fit for drinking purposes.
Refuse
26. The developer must provide waste storage and disposal facilities in accordance with
Planning Scheme Policy No. 9 “Waste Management Multi-Dwellings and Commercial
and Industrial Premises”, including an external imperviously paved area correctly
sized for all refuse and recycling containers and suitably screened from public places
and neighbouring properties.
B. Find the following are sufficient grounds to justify the decision despite the conflict with the
Planning Scheme:
1. ‘Our Backyard’ offers rural type uses which are compatible with and maintains the
rural residential character of the area.
2. The proposal partially fills a gap in support services for people living with disabilities
and their families while not adversely impacting on surrounding rural residential
properties.
3. The proposal will generally add positively to Noosa’s social fabric providing a benefit
to the community and is consistent with the intent of Noosa Social Strategy.
C. Include the Department of Transport and Main Roads conditions as detailed in their
Concurrence Agency response dated 7 November 2016.
Page 11 of 81
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.