2. A minimum of 68 car parking spaces must be provided and marked on the site and made
available and accessible at all times while the use is in operation. The works must be
generally in accordance with the approved plans and the Noosa District Sports Complex
Master Plan 2020-2030. The carparking area must be:
a. constructed with a suitable safe surface,
b. carspaces and access aisles must be suitably delineated, and
c. sealed as part of the subsequent stages of the Noosa District Sports Complex Master
Plan 2020-2030.
9. Stormwater runoff from the development must be disposed of on-site without causing scour
or damage to the subject site or any adjoining property. The stormwater drainage system
must be generally in accordance with the Noosa District Sports Complex Master Plan 2020-
2030 and a whole of site stormwater management plan.
Approved plans
17. Development undertaken in accordance with this approval must generally comply with the
approved plans of development. The approved plans are listed in the following table unless
otherwise amended by these conditions.
Plan No. Rev. Plan/Document Name Date
A01-00 H Site Plan – Demolition prepared by Paynters 15/04/24
A01-01 H Site Plan – Proposed prepared by Paynters 15/04/24
Annotated by Council
A02-00 G Floor Plan prepared by Paynters 12/04/24
A02-02 G Roof Plan prepared by Paynters 12/04/24
A04-00 G External Elevations – Eastern and Western prepared by 12/04/24
Paynters
A04-01 G External Elevations – Northern and Southern prepared by 12/04/24
Paynters
Annotated by Council
A05-00 G Building Sections prepared by Paynters 12/04/24
Building appearance
18. Buildings and structures incorporate colours and textures that blend with and complement
the natural setting through low reflective surfaces and timbers that can fade to grey without
requiring high maintenance. Colours and materials shall be chosen to blend well with the
colours and hues of the surrounding vegetation and landscape without causing glare or
reflection in the violet, blue, green and yellow green side of the spectrum as well as greys or
browns including low gloss metal finishes. Broad expanses of a single colour are less
desirable and where possible should be broken up by other colours or design elements.
Whites or bright colours should be restricted to trimming.
Page 1 of 3
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalFull text of the other 2 pages
Page 2
PLANNING & ENVIRONMENT COMMITTEE MEETING REPORT 10 SEPTEMBER 2024
19. Vandal resistant paint must be incorporated into the finish of the building.
20. The building must include rainwater capture and reuse suitably designed for the roof size
and number of toilets.
Site Access and Driveways
21. An access driveway must be provided from McKinnon Drive to all parking and manoeuvring
areas of the development. The works must be generally in accordance with the Noosa District
Sports Complex Master Plan 2020-2030.
Earthworks and Retaining Walls
22. All earthworks and associated batters must be contained entirely within the subject site
unless written permission from the respective landowner(s) is provided to Council. All
earthworks must be undertaken in accordance with the provisions of Australian Standard
AS3798: Guidelines on Earthworks for Commercial and Residential Developments.
Damage to Services and Assets
23. Infrastructure including reticulated water, sewerage, stormwater, and electricity must be
protected from damage and made safe to the standard required by the regulatory authority.
24. Any damage caused to existing services and assets as a result of the development works
must be repaired at no cost to the asset owner at the following times:
a. where the damage would cause a hazard to pedestrian or vehicle safety, immediately;
or
b. where otherwise, upon completion of the works associated with the development.
Any repair work which proposes to alter the alignment or level of existing services and
assets must first be referred to the relevant service authority for approval.
Landscaping Works
25. Existing trees on the site must be retained, except where required to be removed to
accommodate the approved building. In this regard, the removal of vegetation must not
extend beyond 3 metres of the building footprint.
26. Existing vegetation in the road reserve must be retained, unless written authorisation from
Council is granted for the clearing.
27. Trees to be retained must be protected from clearing or construction activities by:
a. clearly marking vegetation to be retained with flagging tape
a. installing protective fencing around the drip line of the vegetation
b. restricting stockpiling, storage and vehicle parking to those areas which are already
cleared
c. using low impact construction techniques around vegetation.
28. The development site must be landscaped. The works must be undertaken in accordance
with the Noosa Plan for that specific area and must include:
a. provision of dense screen planting for a minimum length of 60m along the Mckinnon
Drive frontage (west of the Sports Complex Entrance) to screen the building from
Mckinnon Drive, in accordance with Planning Scheme Policy PSP2 – Landscaping.
29. All landscape works must be established and maintained in accordance with the approved
design for the life of the development, and in a manner that ensures healthy, sustained and
vigorous plant growth. All plant material must be allowed to grow to full form and be
refurbished when its life expectancy is reached.
Page 2 of 3
Page 3
PLANNING & ENVIRONMENT COMMITTEE MEETING REPORT 10 SEPTEMBER 2024
Demolition
30. All building materials containing asbestos, including asbestos cement sheeting or roofing and
lagging, are removed from the building prior to demolition or relocation.
31. Removal of building materials containing asbestos must be undertaken by a licensed
asbestos removalist.
32. A waste management plan, in accordance with the requirements of Planning Scheme Policy
PSP9 Waste Management, is to be provided to Council for approval prior to the issue of the
development permit for building works.
33. Unless specifically conditioned otherwise, all works must comply with the relevant acceptable
solutions as contained in the Waste Management Code and Water Quality and Drainage
Code of the Noosa Plan.
34. Adequate area must be provided on-site for the collection and separate storage of recyclable,
non-recyclable, vegetative and hazardous materials in their specific waste streams during
removal or demolition works.
35. All waste materials must be removed from the site to avoid causing unhealthy conditions,
with the site left clean, tidy and free from any debris.
36. Where a development permit has not been issued for the future use of the site, hard surfaced
areas including concrete slabs must be removed and disturbed areas must be revegetated
in accordance with PSP2 Landscaping of the Noosa Plan 2020. Alternatively, the site must
be turfed within 20 business days of completing the removal or demolition work.
37. Erosion and sediment control is to be undertaken in accordance with the requirements of the
Water Quality and Drainage Code of the Noosa Plan. Measures are to be installed and/or
maintained until soils are stabilised by vegetation or sealed.
NOTE: It is an offence under the Environmental Protection Act 1994 to deposit or potentially
allow litter, waste, soil, or other contaminants to enter a waterway or storm water drainage
system (e.g. roadside gutter).