24. All stormwater drainage (including roof water overflow from the rainwater storage system) shall be
collected and discharged so there is no net increase in stormwater runoff from the site. Stormwater
drainage permitted to drain from the site shall be discharged to Council’s kerb & channel street drainage
system in Peregian Esplanade. Plans of the drainage design shall be prepared by a Registered
Professional Civil Engineer and submitted to Council prior to obtaining a Development Permit for
Operational Works. The maximum discharge of stormwater drainage allowable to Council’s kerb &
channel street drainage system at any one location is 25 litres/second.
25. All site stormwater drainage shall be by means of a gravity system.
Sewer Mains
26. The site shall be connected to Council’s existing sewerage reticulation systems and be constructed in
accordance with Council’s standards and requirements at no cost to Council.
27. The existing sewer main that is located in the adjoining property at the rear and southern side of the site
and the ‘zone of influence’ (taken as the area within a 45-degree angle measured from the invert of the
sewer main to the finished surface level) shall be accurately located and determined by a licensed
Surveyor and shown on all plans submitted for Operational Works approval.
To ensure Council’s sewer main is accessible for maintenance purposes and is protected from risk of
damage no structures requiring a building permit (eg. buildings, swimming pools, retaining walls
exceeding 1m in height, raised terraces, etc) shall be constructed within this ‘zone of influence’ or within
1.5m of the centreline of the sewer main, whichever is the greater. As such the applicant shall amend
Operational Works plans including Building plans to ensure compliance.
Town Water Supply
28. The site shall be connected to Council’s existing town water supply and be constructed in accordance with
Council’s standards and requirements at no cost to Council.
29. Each individual water connection to the water reticulation system shall extend to the property boundary
and be metered. All fees for the supply of water meters shall be paid to the Council.
30. All water meters must be located outside the property boundary and in an easily assessable location to
facilitate unhindered reading by Council and/or Council’s contracted water meter readers, and not behind
fences or locked gates. In this regard approval of the water meter configuration and location must be
obtained from Council’s Water & Sewerage Capital Works Manager prior to lodgement and approval of
hydraulic drawings.
31. For Multiple Uses (including Building Format Plans, Group Title Plans, etc) the development shall be
served by Individual water meters to each tenement capable of being separately rated.
Service Easements (Sewer)
32. A registered easement shall be created over the zone of influence of all sewers within the subject site and
over those parts of the subject site that are impacted upon by sewers on any adjoining sites. The
easements shall generally be parallel to and centred over the sewer main and be equivalent in width to
twice the depth to invert level of the sewer at the deepest point within the allotment (measured from the
finished surface) and be no less than 3.0m wide overall. In this regard a licensed surveyor shall
accurately locate all sewer mains and determine the necessary width of the easement, which shall be
shown on any plans submitted for Operational Works approval. To this extent the surveyor shall certify
that the sewer and the zone of influence is wholly contained within the easement to be created.
In addition to this the Applicant’s Solicitor shall give Council’s Solicitor an appropriate undertaking in
writing that the Title Deed and the easement documents will be lodged at the Land Titles Office and any
additional Titles Office forms or requisitions requiring the consent of Council will be attended to promptly.
A duly executed copy of the easement shall be submitted to Council for perusal prior to the use
commencing.
Any changes required by Council’s Solicitor must be corrected immediately.
Earthworks
33. Earthworks carried out on site shall not affect the structural integrity of any of the existing fences and/or
structures and/or land that border the development site. Fences that are affected shall be replaced prior
to the Building Certifier issuing the Certificate of Classification. In this regard any fences to be replaced
shall be clearly shown on the plans submitted for Operational Works approval.
AOP2 c:\docume~1\aop2\locals~1\temp\bcl technologies\easypdf 5\@bcl@f00989a5\@[email protected]
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
SUPERSEDED Decision Notice - 010.2007.00001256.001 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 238 KB (small file)
- File type
No other editions are linked here.