Minor Change Existing Approval - MCU25 0136 01 (As Published)
Street Identification
4. The street address of the development must be clearly visible and discernible from the
primary frontage of the site by the provision of a street number and, where appropriate, the
building name.
External Works
5. Olivine Street must be upgraded for the length of its frontage to the subject site. The works
must be undertaken in accordance with an Operational Works approval and must include in
particular:
6. construction of kerb and channelling and underground stormwater drainage to the
development side only. The kerb and channel must be offset 6.0 metres from the existing
kerb and channel on the north-western side of Olivine Street;
7. widening and sealing of the existing road pavement to match the alignment of kerb and
channel;
8. construction of a pedestrian footpath in accordance with the conditions of this Decision
Notice; and
9. upgrading the existing stormwater pit in accordance with the conditions of this Decision
Notice.
Site Access and Driveways
10. A sealed access driveway must be provided from Olivine Street to all parking and
manoeuvring areas of the development. The works must be undertaken in accordance with
an Operational Works approval and must include in particular:
a. a driveway crossover in accordance with Council’s standard drawing RS-051; and
11. a sealed driveway for the full length of the access handle, including visitor carparks and other
servicing and manoeuvring areas.
Car Parking
12. A minimum of 12 car parking spaces must be provided on the site. The works must be
undertaken in accordance with an Operational Works approval, be generally in accordance
with Blackwood’s Site Plan – Ground Level (DA1.08, Rev. F) dated 13 March 2026 and must
include in particular:
a. 2 visitor parking spaces within the total; and
b. dimensions, crossfalls and gradients in accordance with Australian Standard AS2890:
Parking Facilities.
Pedestrian and Bicycle Facilities
13. Pedestrian and bicycle facilities must be provided for the development. The works must be
undertaken in accordance with an Operational Works approval and must include in particular:
a. a 1.5 metre wide footpath within the road verge for the entire length of the site’s
frontage to Olivine Street – the footpath’s width can be reduced (to a minimum of 1.2
metres), only in locations where a 1.5 metre wide footpath would impede on minimum
clearances from services (i.e., light poles) or result in the creation of trip hazards for
pedestrians.
Page 3 of 10
Document Set ID: 25046953
Version: 4, Version Date: 17/08/2026
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original (Minor Change Existing Approval - MCU25 0136 01 (As Published).pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.