4 Proposed Development
4.1 Proposed development
A total of 10 x two-bedroom residential apartments are proposed at the rear of the development across the
ground and first floor. A total of 768 square metres of Commercial spaces are proposed on the ground floor
at the front of the site.
A basement car park is proposed across most of the site with vehicular access to and from Doonella Street.
The proposed development plans that are the subject of this Traffic Impact Assessment are appended to this
report.
4.2 Traffic Generation
An indication of the traffic generation potential of the development proposal is provided by reference to the
Roads & Maritime Services Guide to Traffic Generating Developments, Section 3 – Land use Traffic
Generation (October 2002).
The RMS Guidelines are based on extensive surveys of a wide range of land uses and nominate the
following traffic generation rates which are applicable to the development proposal:
Application of the above traffic generation rates to the various components outlined in the development
proposal yields a traffic generation potential of 20 peak hour vehicle trips as set out in the table below:
Table 4-1 Peak Hour Development Traffic Generation
Land Use Generation Rate GFA/No. Units Total Trips
Medium Density 0.4 – 0.5 peak hour
Residential Flat Buildings vehicle trips / 1 & 2 10 4-5
bedroom dwellings
Office & Commercial Evening peak hour vehicle
trips = 2 per 100 m2 gross 728 m2 15
floor area.
Total Trips Generated 20
The projected future level of traffic activity should however, be offset or discounted by the level of traffic
activity which could reasonably be expected to have been generated by the previous uses of the site, in
order to determine the nett increase in the traffic generation potential of the site as a consequence of the
development proposal.
Application of the “previous” traffic generation rate nominated in accordance with the RMS Guidelines of
Traffic Generating Developments for the existing land uses for both sites is provided below:
Table 4-2 Peak Hour Existing Traffic Generation
Land Use Generation Rate GFA/No. Units Total Trips
Residential dwelling
0.9 peak hour vehicle trips 1 0.9
house (No. 30 Doonella)
Residential units 0.5-0.65 peak hour trips 1 x 3 bed 0.5-0.65
(No 32 Doonella) 0.4-0.5 peak hour trips 4 x 2 bed 1.6-2.0
0.4-0.5 peak hour trips 1 x 1 bed 0.4-0.5
Total Trips (existing) 3.4 - 4.05
Adopt 4 trips
12 February 2017 Greys 14
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original (16216_Parking & Traffic Impact Assessment Report_1502017.pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.