SITE EROSION AND SEDIMENT PLAN
PROPOSED CHILDCARE CENTRE, SUNSHINE BEACH GC Cardno

 

EXECUTIVE SUMMARY

This report is for the Site Erosion and Sediment control measures associated with the
construction works for a Childcare Centre Development at 71 Pacific Avenue, Sunshine
Beach. This report is to be read in conjunction with all the engineering plans for the site and
the relevant statutory approvals for the site.

1. SITE EROSION AND SEDIMENT HAZARD

Where practical the soil erosion hazard is to be kept as low as possible, at all times.

1.1 Hydrologic impact

During construction the potential exists for impacts on downstream drainage systems and
ultimately water bodies. This is to be ameliorated by the provision of silt fences and inlet
filters thereby minimising the majority of potential impact on downstream drainage systems
and ultimately water bodies.

1.2 Site Physical Characteristics Constraints and Opportunities
The development site has the benefit of being partially enclosed by a recently constructed
concrete block wall. This wal! has the benefit of containing all of the surface runoff from the
internal site and thus gives the opportunity to prevent sediment entering the drainage
system.

1.3 Erosion Hazard Assessment

The following hazard factors have been considered in putting together the Soil Erosion and
Sediment Control Plans.

1.3.1 Soil Type
The soil type is generally classified as sand and is deemed to be of ow risk.
1.3.2 Slope

The existing topography of the site slopes at approximately 7% towards the David Low Way
and Pacific Avenue intersection.

1.3.3 Duration of Soil disturbance

It is intended that the entire construction program will take no more than 24 weeks, with the
earthworks portion of the work taking only 6 weeks. Upon completion of earthworks, the
site will be stabilised and inspected by the Engineer.

1.3.4 Waterway Disturbance

No significant waterways are to be disturbed as a part of these works.

 

COMISKEY GROUP Version 1 18 June 2008
238401 ML Site Erosion and Sediment Report.doc = Commercial in Confidence Page 1

Used in these records

About this file

File size
11.2 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

08_1056 - Operational Works - Roadworks, Stormwater & Earthworks [As Published].pdf · 11.2 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.