Division 14—Earthworks Code
The Noosa Plan
14.115 Earthworks Code
The provisions in this division comprise the Earthworks Code. They are—
compliance with the Earthworks Code (section 14.117);
overall outcomes for the Earthworks Code (section 14.118); and
specific outcomes, acceptable solutions and probable solutions (sections 14.119—
14.120.
14.116 Compliance with the Earthworks Code
Development that is consistent with the specific outcomes in sections 14.119—14.120
complies with the Earthworks Code.
14.117 Overall outcomes for the Earthworks Code
14.117.1 The overall outcomes are the purpose of the Earthworks Code.
14.117.2 The overall outcomes sought for the Earthworks Code are the following—
a) To ensure that earthworks do not unreasonably impact on the natural environment or other
properties with regard to—
i land stability (including differential settlement or expansion in reactive soils);
ii contamination of land;
iii flooding and drainage;
iv groundwater, watercourses and wetlands;
v loss of native remnant or regrowth vegetation; and
b) Earthworks are designed and constructed to be structurally sound.
14.118 Specific outcomes, probable solutions and acceptable solutions for
the Earthworks Code
The specific outcomes sought for the Earthworks Code are included in column 1 of Table
14-52. Acceptable solutions for accepted development subject to requirements and
probable solutions for code assessment development are included in column 2 of Table
14-52.
Table 14-52 — Earthworks
column 1 column 2
Specific Outcomes Acceptable solutions (if accepted
development subject to requirements)
Probable solutions (if code assessment)
14.119 Effects of works
Drainage
O1 Finished surface levels ensure land is free S1.1 The finished surface gradient of any filled
draining. or excavated area is within the range 0.5% to
1.5% and drains to Council’s stormwater
infrastructure where available or where
stormwater infrastructure is not available,
toward the street.
Hydraulics
O2 Any change to the level of the land does No solution provided.
14-126
Earthworks Code
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLarge file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.