Specific Outcomes Acceptable solutions (if accepted
The Noosa Plan
development subject to requirements)
Probable solutions (if code assessment)
site or nearby land; and areas are constructed at a level that permits the
ii. increasing flooding, which parking area to drain from the site by gravity
adversely affects the safety or use means, without the need for mechanical
of any land upstream and pumping;
downstream; and AND
iii. adversely affecting the flow of S2.3 Filling, other than accessways, does not
water in any overland flow path; extend more than 1m beyond the footprint of
iv. adversely affecting the privacy or any building, measured from the outer walls of
visual amenity of surrounding the building.
properties.
AND
O3 Finished surface levels ensure land is free S3.1 No solution provided
draining.
Editor’s note:
Council encourages building methods that
avoid the use of fill such as suspended floor
construction and stepping down slopes
rather than cutting and filling.
O4 Filling or excavation does not adversely S4.1 Fill material placed over services does not
affect sewer, stormwater or water utility impose any additional surcharge loading on the
infrastructure. service.
S4.2 Where excavation is carried out-
a) a minimum cover of 600mm is maintained
around all utility infrastructure (to top,
sides and base of services); or
b) a retaining wall is provided to support the
soil surrounding the service;
AND
S4.3 Compaction with a vibrating roller is not
carried out within 600mm of any utility
infrastructure.
O5 Development does not adversely impact S5.1 Buildings or other structures within the
on the Lake Macdonald water supply. Lake Macdonald catchment (indicated on Figure
14.7) are located above the 98.5m AHD level.
Services and Utilities
O6 The house is provided with infrastructure, S6.1 Where located in an urban zone, or a
services and utilities appropriate to its setting. water or sewerage service area, appropriate
connection is provided to reticulated sewerage,
water supply and stormwater drainage.
Electricity supply infrastructure
O7 Uses and works maintain an adequate S7.1 Buildings and structures (including
safe distance from electrical infrastructure swimming pools, sheds, tennis courts or
including substations, overhead powerlines, outbuildings) are not constructed under
power poles and transformers. overhead electricity transmission lines, or within
electricity easements.
Water Supply Infrastructure
O8 Existing water supply infrastructure, S8.1 Buildings and structures are setback a
including pipeline corridor, is protected from minimum of 20m from a water supply pipeline
incompatible development to ensure the safety as shown on Overlay Map OM3.5.
and reliability of water supply network.
Steep Slopes and Landslide hazard areas
O9 Detached houses, Ancillary dwelling S9.1 If on premises identified as a Landslide
14-59
Detached House Code
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLarge file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.