EngSWMP

Attached to the e-mail Response to Information Request MCU16/0079 (email 2 of 3).

of 94

Page text read automatically using OCR, there may be inaccuracies

                                                                                                            ENG
                                               Engineering Report & Stormwater Management Plan
                                       Date:          22/09/2016     Document No.:      16144-ENG-01.Docx

                                        By:               MRS         Revision No.:              A


                     d. MUSIC Model Results
Using the MUSIC software the treatment train for the catchment areas was designed to
comply with the water quality objectives (WQO). It was determined that the water quality
objectives for the proposed development where met as shown in the table below:

                                 Pre-       Post-                  Reduction          Complying
  POLLUTANT TYPES
                             Development Development                  (%)             With WQO
 Total Suspended Solids
                                 556               111                80                  
         (kg/yr)
   Total Phosphorus
                                1.24              0.302              75.6                 
         (kg/yr)
  Total Nitrogen (kg/yr)        9.57               4.88               49                  
 Litter/gross pollutants
                              67.5             0              100                         
         (kg/yr)
     Table 5.5:      Stormwater360 Water Quality Treatment Results

As shown by the above results, the proposed stormwater treatment train adopts best practice
stormwater treatment and will achieve the required Water Quality Objectives.

                     e. Stormwater Quantity Management
Noosa Regional Council Policy requires that a development ensure non-worsening of
stormwater flows up to and including Q100 stormwater events. The proposed development
will not have a larger impervious area than the existing developed site and hence will not
require a stormwater detention system to mitigate the effects of any additional runoff.

                     f. Maintenance

    Construction Phase Management Plan
Potential construction phase impacts include the following:
 Sedimentation and erosion
 Management of contaminated soils and materials on the site Construction Material (such
    as cement)

     General
The objective of the Construction Phase Management Plan is to comply with the requirements
of the Queensland Environmental Protection Act 1994 and Environmental Protection (Water)
Policy 2009 so that the environmental values of effected receiving waters are maintained or
enhanced. In essence the purpose of the Plan is to prevent polluted stormwater being
discharged to the local waterways.




A PO Box 26, Carina Q 4152                                                                 11 | P a g e
E [email protected]
W www.vtce.com.au

Log in to download the original (EngSWMP.PDF)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.