EngSWMP
Attached to the e-mail Response to Information Request MCU16/0079 (email 2 of 3).
ENG
Engineering Report & Stormwater Management Plan
Date: 22/09/2016 Document No.: 16144-ENG-01.Docx
By: MRS Revision No.: A
8. Water Reticulation
Figure 7.1 shows the existing water reticulation infrastructure for the proposed site. Hydrants
are situated adjacent to the site in Memorial Avenue and Doonella Street.
A new water connection will be provided from the supply in Memorial Avenue to the
proposed development to Unitywater and SEQwater standards.
The Internal water supply design for this proposed development will be by others.
9. Electrical and Telecommunication
The electrical supply and communications supply for this proposed development will be by
others.
10.Development Codes
The following applicable Local and State Codes have been completed to address the proposed
development and are included in Appendix H:
Driveway and Parking Code
Earthworks Code
Water Supply and Sewerage Reticulation Code
11.Conclusions
vT Consulting Engineers has undertaken a review of civil engineering services required for the
proposed development located at 1 Memorial Avenue, Tewantin QLD 4565.
Based on all the findings outlined in this report, vT Consulting Engineers believes that there are
no significant engineering issues in relation to this development.
A PO Box 26, Carina Q 4152 15 | P a g e
E [email protected]
W www.vtce.com.au
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original (EngSWMP.PDF)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.