EngSWMP
Attached to the e-mail Response to Information Request MCU16/0079 (email 2 of 3).
ENG
Engineering Report & Stormwater Management Plan
Date: 22/09/2016 Document No.: 16144-ENG-01.Docx
By: MRS Revision No.: A
developments below 20.0m AHD that involve a Material Change of Use or operational works
are required to be assessed against the SPP 2016 acid sulphate soils development objectives.
As the lowest point on this site is an approximate level of RL5.0m, we believe there is a
possibility of acid sulphate soil being present and therefore testing may be necessary.
The requirements for Acid Sulphate Testing will be confirmed by a geotechnical engineer prior
to the detailed design stage of this proposed development.
Land Disturbing Activities
Important causes/issues of erosion for this site would consist of the following:
Precipitation and consequent run-off
Stripping and removal of topsoil
Removal of fill
Other earthwork operations
Heavy vehicle use on site
Wind erosion
The proposed development is a short construction period which will be programmed so that
the shortest period of time elapses between ground cover removal and restoration.
Erosion and Sediment Control Measures
Sediment control filter fabric will be securely placed around the perimeter of the construction
site. This will ensure sediment is trapped before being released into the catchment. Refer
Appendix D.
An ESC measure will be provided at any vehicular access points to the site. Construction and
maintenance details are given in Appendix D. A temporary construction entrance will be
provided from Pelican Street for access during construction.
A filter sock sediment trap will be utilized on all downstream stormwater inlets. Refer
Appendix D for construction and maintenance details.
No clearing will be undertaken unless preceded or accompanied by installation of adequate
run-off and sediment control measures, as described above.
Following practical completion of the project a minimum of 70% coverage of all soil with
ground cover (i.e. topsoiling and seeding) will be provided within 30 calendar days.
During the construction phase spraying of water will be used with care to act as a dust
suppression method.
Monitoring and Maintenance Programs
Water discharge from the site will adhere to a total suspended solid content of less than 50
milligrams per litre and a pH range of between 6.5 and 8.5 at all times. If the pH of the
A PO Box 26, Carina Q 4152 5|P a g e
E [email protected]
W www.vtce.com.au
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original (EngSWMP.PDF)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.