PLANNING & ORGANISATION COMMITTEE MEETING AGENDA 8 DECEMBER 2015
‘The Noosa Plan was first gazetted in February 2006. State legislation requires Council to
undertake a comprehensive review of the planning scheme every 10 years. This would make
a review due no later than 2016… it is not recommended that Council attempt to prepare a
new planning scheme within this term of Council due to the resources required, time
involved and upcoming state legislative reforms. Rather it is recommended a review of the
scheme be completed in the second half of 2015 with a view to commence preparing a new
scheme in 2016. In the meantime, it is proposed to amend the current scheme to deal with
pressing issues until a comprehensive review is commenced.’
Ordinary Meeting, 6 March 2014 Item 3, Pg 7
That Council note the report by Project Leader, Strategic Planning, Planning & Development
to the Planning & Organisation Committee dated 25 February 2014 and:
A. Resolve not to proceed with the previous Sunshine Coast Regional Council Draft
Planning Scheme process which applied to the Noosa Shire area;
B. Resolve to commence the process of making planning scheme amendments to the
Noosa Plan;
C. Authorise the Chief Executive Officer to advise the Minister of Council’s proposal to
commence the process of making planning scheme amendments; and
D. Respond to persons who made Noosa-relevant submissions to the draft Sunshine
Coast Planning Scheme in 2012 to advise them of Council’s intention regarding a
planning scheme review.
Following the first State Interest Review and Public Consultation process, Council resolved
to proceed with amendments to the Noosa Plan at the Ordinary Meeting of 19 November
2015. Subject to a timely second State Interest Review, these are likely to commence in the
first quarter of 2016.
Finance & Risk
A breakdown of the estimated project costs is provided in Attachment 1, an extract of which
is shown below. The project brief will be provided as part of the 2016/17 capital works
budget development process and the five year capital programme will include budget
estimates of the forward programme as detailed below.
The current capital works budget and forward programme includes an allocation of $360,000
for employee costs over the next three years, and $100,000 in 2016/17 for consultancy,
however, these figures will require revision based on the updated budget estimates and
timelines in the project brief.
Capital $
Estimated Project Funding 2016/17 2017/18 2018/19 Total Project $
Employee/ salary costs (including
oncosts) $546,963 $560,638 $574,653 $1,682,254
Materials & Services $0 $10,000 $61,000 $71,000
Other costs (legal & consultant fees) $0 $167,680 $57,520 $225,200
Total Project Investment $546,963 $738,318 $693,173 $1,978,454
Page 30 of 68
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.