PLANNING & ORGANISATION COMMITTEE MEETING AGENDA 8 DECEMBER 2015
ENGINEERING
Boundary Encroachments
13. Certification must be submitted to Council from a Licensed Surveyor which certifies
that:
a. the boundary clearances for any existing buildings remaining on the site comply
with the relevant provisions of the planning scheme and the Building Act 1975,
unless varied by this Decision Notice;
b. all constructed access and roadworks (including associated fill batters and
retaining walls) are fully contained within a dedicated reserve or registered
easement; and
c. all utility services and connections (eg. electricity, telecommunications, water,
sewerage) are wholly located within the lot they serve or alternatively included
within an easement.
Water & Sewer Connections
14. An underground connection to reticulated water and sewerage must be provided to
each lot in accordance with the standards and requirements of Northern SEQ
Distributor–Retailer Authority (Unitywater).
15. A Certificate of Completion from the Northern SEQ Distributor–Retailer Authority
(Unitywater) must be submitted to Council that certifies an underground connection to
reticulated water and sewerage has been provided to each lot.
Performance Bond
16. Security in the form of a cash bond or trading bank guarantee to the sum of $50,000
must be submitted to Council, to secure performance of all conditions of this approval,
prior to the issue of a Development Permit for Operational Works. The cash bond or
trading bank guarantee will be returned on performance of the conditions of approval
less any costs incurred by Council in respect of enforcing performance of this permit.
Council reserves the right to call upon the bond or guaranteed sum to effect
compliance with conditions.
Frontage Works
17. George Street must be upgraded for the length of its frontage to the subject site. The
works must be undertaken in accordance with an Operational Works approval and
must include in particular:
a. Construction of kerb and channelling and as may be reasonably extended
beyond the frontage of the site;
b. Any necessary adjustment to the road’s pavement and sealing;
c. Any necessary adjustments or repairs to the existing concrete footpath due to
the development works;
d. Street stormwater drainage collection and disposal to a legal point of discharge
including any stormwater quality treatment devices where required;
e. Grassed verge at batters generally not steeper than 1:4; and
f. Landscaping as specified within this approval.
This condition is imposed pursuant to s665 of the Sustainable Planning Act 2009 being
non-trunk infrastructure.
Page 7 of 68
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.