Table 7.2.6.3—Coastal Communities Local Plan Code
Performance outcomes Acceptable outcomes Response
c. is serviced by a conveniently located hosecock and
backflow prevention device, and connected to a water
supply; and
d. is roofed or otherwise covered if the storage area is—
i. more than 1m²; or
ii. storing wet waste; or
iii. storing other waste with a high potential to
cause pollution if washed or leaked from the
bins, including waste oil or putrescibles.
Safety and protection of infrastructure when demolishing or removing buildings
PO7 AO7.1 Complies
Demolition, removal, relocation or associated works do not result in: Infrastructure including reticulated water, sewerage, stormwater, Infrastructure will be appropriately dealt with and made safe during
a. 'live' or 'active' infrastructure that may present risk to and electricity are protected from damage and made safe to the construction.
people using the site or surrounding areas; or standard required by the regulatory authority.
b. damage to infrastructure or other works. AO7.2 Complies
Infrastructure is disconnected, capped or sealed including: Infrastructure will be appropriately dealt with and made safe during
Editor's note— An approval will be required from Council's Building a. electricity meters are removed and electrical wires construction.
and Plumbing Services for decommissioning plumbing apparatus disconnected;
including: b. telephone lines are disconnected; and
sanitary drains or reticulated water supply; and c. data cables are disconnected and removed.
septic tanks, holding tanks or on-site treatment systems. AO7.3 Complies
A temporary crossing is provided to protect road reserve A temporary crossing can be provided if deemed necessary during
infrastructure including kerb and channel. construction.
AO7.4 Complies
Any damage to footpaths, street plantings, natural vegetation, kerb Any damage will be repaired and made good following construction.
and channel, bridges or roadways at the removal site, the new site
or between the sites is repaired or reinstated to at least pre-existing
conditions.
PO8 AO8.1 Complies
Waste materials are removed from the site to avoid causing Waste materials are removed from the site. Waste materials will be removed from the site.
unhealthy conditions including: AO8.2 Complies
a. potential fire hazard; If a development permit has not been issued for the future use of the If a development permit has not been issued following demolition
b. ponding of water; and site: appropriate site works will be undertaken.
c. breeding of vermin. a. hard surfaced areas including concrete slabs are removed
or covered with a minimum of 300 millimetres of soil; and
Town Planning Report - 65-67 Elanda Street, Sunshine Beach 74
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.