Paving Treatment of Vehicle Movement Areas
30. Alternative materials, patterns, or threshold treatments must be used to articulate the
pavement treatment of vehicle movement areas.
Service Vehicles
31. Service vehicle parking, manoeuvring and standing spaces must be provided on the site.
The works must be undertaken in accordance with an Operational Works approval and be
in accordance with Council’s Planning Scheme Policy 9 – Waste Management. The
development must include in particular delivery/service/waste areas that are accessible by
a 12.5m vehicle.
Pedestrian and Bicycle Facilities
32. Pedestrian and bicycle facilities must be provided for the development. The works must be
undertaken in accordance with an Operational Works approval and must include in
particular:
a. a 1.8 metre wide footpath within the road verge for the entire length of the site’s
frontage to Pelican Street and Doonella Street. The path must be extended to the
existing full width path in Memorial Avenue
b. signage and lighting at strategic locations to direct people to building entries
c. a total of 13 bicycle parking spaces
Stormwater Drainage
33. The site must be provided with a stormwater drainage system connecting to a lawful point
of discharge. The works must be undertaken in accordance with an Operational Works
approval and must include in particular:
a. a stormwater drainage system that collects and discharges runoff such that there is
no net increase in stormwater runoff from the site.
b. the use of gravity stormwater drainage and not surcharge pits.
Stormwater Quality Management
34. A stormwater quality treatment system must be provided for the development. The works
must be undertaken in accordance with an Operational Works approval and achieve the
pollution reduction targets of the State Planning Policy Appendix 2 Water Quality and be
modelled in accordance with the Water by Design MUSIC modelling guidelines or the
Water by Design deemed to comply solutions.
35. Stormwater quality treatment devices must be routinely checked, serviced and cleaned in
accordance with the manufacturer’s recommendations or Water by Design “Maintaining
Vegetated Stormwater Assets” guidelines. Records of all maintenance activities undertaken
must be kept and made available to Council upon request. Where replacement cartridges
or other necessary components for the system become unavailable, an alternative system
is required to be retrofitted into the development to achieve an equivalent pollutant
reduction outcome.
36. All primary stormwater quality treatment devices must be routinely checked, serviced and
cleaned in accordance with the manufacturer’s recommendations. Records of all
maintenance activities undertaken must be kept and made available to Council upon
request.
37. The ongoing maintenance plan for the development must include the operations and
maintenance manual for the water quality device/s and must include the full cost of
maintaining the system. This maintenance plan must be provided as part of the subsequent
operational works.
Page 8 of 61
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.