Part C - Attachments E to G

Attached to the e-mail Other Change Application – 132002.220285.5.

of 69

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Very large file: it may take a few minutes

The original of this document is very large (15.1 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Original PDF page 26, section 1. The text section number identifies this passage in the reader.

319


[OCR of page images]
NOOSA COUNCIL IDAS Development Application Decision Notice 25

173.17.

173.18.

173.19.

173.20.

173.21.

173.22.

173.23.

173.24.

173.25.

173.26.

173.27.

During the establishment and operational phases the applicant is to undertake inspections
for erosion and deposition, and build up of trash and gross pollutants, and other water
pollution. These inspections will be carried out after significant rainfall events, and on a
three monthly campaign basis for a period of five years from completion of the final stage of
construction. Corrective measures will be implemented where indicated by such
inspections.

For the construction phase at least four per year event based water quality monitoring shall
be undertaken for:

° Suspended Solids & Turbidity.
. pH.

° Temperature.

° Salinity.

° Trash & gross pollutants.

In addition to the above, inspections for erosion and deposition, and build up of trash and
gross pollutants shall be carried out on a weekly basis during the construction period and
corrective measures implemented.

An operational phase Water Quality Management Plan shall be prepared to address water
treatment device water quality maintenance requirements for stormwater management
measures and devices, contingency measures for aquatic plant growth, loss of vegetation in
swales, die off of trees and shrubs in or near any devices, pollution response and algal
blooms and shall include a mosquito management strategy. The plan shall demonstrate
compliance with the water quality objectives set and a no worsening over the existing pre-
development situation in the site gullies, OS1, OS2 and OS4, in Eenie Creek and the
freshwater dam.

Responsibilities for all actions required in the plan are to be clearly delineated.

Non-compliance with prescribed water quality standards shall trigger the implementation of
measures/further testing to rectify.

Monthly reports on monitoring, incidents, corrective action and plan updates are required to
be submitted to Council during the construction period. These reports are to be submitted
in a form acceptable to the Manager Land Development (including digital form) and are to
highlight any non-standard results.

Yield analysis using a 3-hour (maximum) timestep MUSIC or equivalent model is required.
This analysis will need to demonstrate the effect of the proposed works on the water cycle
in OS1, OS2, OS4, OS5 and OS7. This modelling shall be undertaken and submitted with
the application for operational works

The use of enhanced existing vegetation filtration or alternate methods not requiring
clearing is to be used for drainage works to OSS, instead of the proposed construction
extended detention basins.

Deleted.

The bio-retention devices shall be maintained by the applicant in good working order at all
times, so as to achieve their intended purpose including periodic replacement of sand and
soils. Inspection of the bio-retention devices shall occur at least once every 5 years, and will
provide a written report to the Manager Land Development as to their condition and any
remedial action taken or proposed to be taken.

Deleted.

174. All stormwater design and construction on the development will be undertaken in accordance with the
approved Stormwater Management Plan.

A o\databaselonestop\decision.dac

319

 
Log in to download the original file

Part C - Attachments E to G.PDF · 15.1 MB (very large file)

Very large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.