refer to Level 3 Floor Plan for
details of roof works to this roof
new s/steel flue - installation
to NCC 3.7.3 req'ts
ex.gutter to remain new flue
20°
fall
exist. steel outriggers to this
roof to remain - to be patched / exist. custom orb roof
treated & refinished as spec. sheeting to remain to this
exist.
10° fall
roof - exist. solar pool exist. steel outriggers to this
20° fall
20° fall
exist.
exist.
heating system to remain roof to remain - to be patched /
treated & refinished as spec.
exist. wall capping under - to be
repaired / replaced if needed - cos
min.1:100
fall exist. roof sheeting / outriggers to remain - steel
20°
outriggers to be patched, treated & refinished as spec.
fall
20°
fall
20°
fall
new roofing to higher section roof (replaced with
exist. box gutter to be rectified / make good exist. roof sheeting ex.gutter to remain exist. roof sheets that have been removed from
p.c alum louvred L2 roof (only if suitable / in good condition) -
where water damage - new structure where to remain exist. steel purlin/s under higher higher section roof to be removed
retractable roof exist. box gutter under - to steel purlins under to be patched, treated &
required / new waterproof membrane with section roof to be replaced (replaced with exist. roof sheets that
structure below - over be rectified due to exist. refinished as spec.
new falls req'd min.1:100 have been removed from L2 roof (only
Level 2 outdoor dining water damage / make good
if suitable / in good condition)
new solar panels / option only for costings - to be
confirmed - option to have approx. 16 panels (3kW
system on upper level roof & roof over bed 1
nb:
01 ROOF PLAN - typ. to all - exist. flashings to windows / roof areas to be treated & refinished as
walls / fixtures to be demolished - make good where req'd
spec. where req'd (unless noted to be replaced) typ. 90mm internal stud wall - u.n.o.
- 1:100@A3 / 1:50@A1
- all roof screws to be checked / installed correctly - perpendicular to the sheeting in
0
existing wall/s to remain (make good as req'd)
1.0 2.0 5.0m the middle of the rib for maximum water tightness
01 ENGINEERING & CERTIFICATION ISSUE 19.05.2020
Issue Amendment Date
bsa lic.no.1071865
The design & drawings shown on these PROJECT DRAWING TITLE SCALE DWG No. ISSUE
1:100@A3 / 1:50@A1
plans are copyrighted and remain the Alterations & Extensions for Goetz Maeuser & Louise Biddell Proposed ROOF PLAN
property of 'georgina price design'. No
unauthorised copies shall be made. 8/27 Ross Crescent, Sunshine Beach Q DATE
May 2020
A.09 01
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
proposal plans.pdfRelated documentApplication case desk ↗
About this file
- File size
- 2.1 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.