GENERAL COMMITTEE MEETING AGENDA 16 MAY 2022
Page 76 of 96
GENERAL COMMITTEE MEETING AGENDA 16 MAY 2022
Corporate Plan Key Operational Initiatives Outcomes Responsible Update Status Q2 is)
Focus Areas Areas/Officers
2.6 Explore options | Pre-Feasibility Study Noosa | Options and scenarios for a Director Invitation to Quote finalized and contractor Ontrack | On track
for and investigate | Regional Gallery (Stage 2) new regional art gallery are) Community selected. Inception meeting arranged. Intent for
the feasibility of analysed to assist Council | Services final report in September/October.
relocating the in deciding whether or not
Noosa Regional to proceed to a further
Gallery stage in this project
2.7 Plan for Deliver Ageing Well Noosa Assistance provided to Community State Government funded. Launched in October | Ontrack | On track
Noosa's aging program older members of our Development’ | 2021. Further information on what is available to
demographic and community to continue Community Seniors can be found here -
support our health living an active and fulfilling Development https:/Avww.noosa.qid.gov.au/seniors-1
and aged care life Manager
sectors
2.8 Maintain the Review of Noosa Local Increased local area Director Review of the Local Disaster Management Plan | Ontrack | Behind
ability to respondto | Disaster Management Plan | capability for prevention _ Infrastructure | has been broken into 3 tasks as below. Schedule
disaster events preparedness, response Services
(LDMP) and recovery in a disaster Task-1: Project inception & Hazard scenario
generation: This task is now complete.
Task-2: Preliminary risk assessment: This task
is complete.
Task-3: Stakeholder engagement: Task is
underway but experiencing a minor delay due to
covid at the beginning of the year and recent
flood events.
Support the community in Increased community Director Supported second anniversary commemoration of Ontrack | On track
the ongoing recovery efforts | health and wellbeing Community 2019 bushfires. Current focus on developing
from the 2019 Bushfires and Services emergency planning for vulnerable communities
COVID-19 in aged care and disability sectors through Perso
Centred Emergency Preparedness framework.
Page 76 of 96See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.