PLANNING & ENVIRONMENT COMMITTEE MEETING AGENDA 11 JUNE 2019
On 21 April 2009, Council issued a conditional Preliminary Approval for Operational Works
– Drainage, Stormwater, Vegetation Clearing, Water & Sewerage, Earthworks and Access
and Parking. A conditional Preliminary Approval was issued on the basis that payment of
contributions and bonds was outstanding.
On 13 July 2009, Council extended the relevant period of the Ministerial approval and the
associated Operational Works preliminary approval until the 15 October 2013.
On 11 October 2013, a request to extend the relevant period of both the Ministerial
Approval and associated Operational Works preliminary approval was lodged with Council.
This request was refused by Council on 1 May 2014 for the following reasons:
1. The development is contrary to The Noosa Plan’s Overall and Specific Outcomes for
the Noosa Heads Locality;
2. The application was publicly notified in 2004 and given the time lapsed, the
community is unlikely to be aware of the development approval; and
3. The proposed development were it to be publicly notified today, is likely to receive
submissions objecting to the development, given the significant non-compliance with
The Noosa Plan.
An appeal was subsequently lodged in the Planning and Environment Court by the
applicant. The appeal was subsequently withdrawn with the appellant agreeing to
pay some of Council’s preliminary appeal costs. On this basis this development
approval has now lapsed.
On 31 October 2013, the Department of State Development, Infrastructure and Planning
extended the relevant period of the State Permit for clearing of vegetation for two (2) years.
This approval has now lapsed.
Several pre-lodgement meetings were held with the applicant to discuss potential development
outcomes on the site. At the meeting it was discussed that the existing Detached and Attached
Housing zones may not represent the most developable area for the site on the basis they are
steep, likely require access across the creek and removal of some of the better quality vegetation
on the site.
It was considered that the site’s south west corner may provide a better development outcome
based on more moderated slopes and environmental values. However, any development in this
area should be of a scale and density consistent with existing and permitted development in the
street, which are predominantly duplexes.
Further any proposed development should be setback at least 10m from the creeks top of bank,
a wildlife corridor of at least 50m should be retained through the site and the development
sensitively designed to respect the vegetated public walkway.
Page 69 of 133
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.