Earthworks
30. All earthworks and associated retaining structures/batters must be undertaken in accordance
with an Operational Works approval and contained entirely within the subject site unless
written permission from the respective landowner(s) is provided to Council.
31. The development of the site must not adversely impact on adjacent properties, upstream or
downstream of the site, due to changes in flood levels or flood characteristics.
Damage to Services and Assets
32. Any damage caused to existing services and assets as a result of the development works
must be repaired at no cost to the asset owner at the following times:
a. where the damage would cause a hazard to pedestrian or vehicle safety, immediately;
or
b. where otherwise, upon completion of the works associated with the development.
Any repair work which proposes to alter the alignment or level of existing services and assets
must first be referred to the relevant service authority for approval.
Car Parking
33. Existing car parking on site, as detailed on the approved plans, must be maintained and kept
available for users of the Cooroy Sportsgrounds.
34. All car parking areas and access driveways must be maintained exclusively for vehicle
parking and manoeuvring and kept in a tidy and safe condition at all times.
35. A minimum of 13 bicycle spaces must be provided. The bicycle spaces must be positioned
in a location that allow for casual surveillance.
Landscaping Works
36. The development site must be landscaped. The works must be undertaken in accordance
with the Noosa Plan 2020 for that specific area and must include in particular:
a. landscape solutions that reduce the visual impact of building bulk;
b. provision of canopy trees;
c. shrubs and garden beds to clearly define pedestrian walkways;
d. use of screen planting to conceal service and loading areas;
e. planting design and species selection that can endure an intensively used environment
and avoids the use of formal planting design;
f. retention of the existing trees.
Rehabilitation
37. Existing trees on the site must be retained.
38. Rehabilitation Works must be undertaken in accordance with Planning Scheme Policy PSP2
– Landscaping and rehabilitation best practice. The rehabilitation must include:
a. Removal of all weed species, including declared plants under the Biosecurity Act 2014
and sub-ordinate Regulation 2003 and the Noosa Local Government Area Pest
Management Plan 2015-2019.
b. rehabilitation works to the area covering 10 metres along the site’s eastern boundary
with Cooroy Creek for a minimum distance of 50 metres;
c. planting density must be 1 tree at 3m centres and shrubs at 2m centres, with tree
species representing at least 30% of the total plants;
d. 75mm tube stock (pot size) plants;
Page 25 of 28
Document Set ID: 22731989
Version: 4, Version Date: 29/01/2024
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.