Stormwater Management Plan

of 40

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Very large file: it may take a few minutes

The original of this document is very large (11.7 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Plans and drawings

This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).

Log in to see the plans as drawn
STORMWATER MANAGEMENT AND MAINTENANCE PLAN

 

aes MAINTENANCE OF RAPID INFILTRATION PITS (RIP’s)
1. Objective To ensure ongoing function of RIP’s in reintroducing
runoff into the subsoil and prevent
surcharge/flooding.
Consequences of | Possible flooding of building during storm events.
Failure
2. Management Strategy | RIP internal surface to remain free of silt/sediment

build-ups.

RIP grates to remain clear and free of debris or
blockages.

 

Actions

Maintenance Contractor to be issued with
laminated copies of final ALTA Projects drawings
A6769/22/PD01 to PDO5 for reference.

Swales and RIP surface grates to be kept clear of
any debris or blockages.

Maintenance contractor with appropriate
enclosed spaces qualifications and procedures in
place to enter each RIP to inspect at quarterly
intervals and after any event where more than
50mm of rain has fallen.

Any debris, leaf litter etc accumulated in the RIP to
be removed and disposed of lawfully.

Upper BIDIM A14 filter layer to be inspected and if
more than 50% covered in silt or mud replaced.

Upper BIDIM A14 filter layer to be replaced
annually.

When replacing upper filter, the sand layer below
to be inspected for discolouration and
contamination and if present ALTA Projects to be
notified for review and further advice.

RIP walls and balance pipes to be inspected for
any signs of cracking or degradation. If observed
ALTA Projects to be notified.

All removed filter layers, sand, sediment, silt to be
disposed of lawfully.

 

Performance Indicators

No surcharging of RIPs.
No overflow from rock pitched weirs

 

Frequency/Deadline

Inspections after rain events or quarterly
(whichever comes first)

 

 

 

Reporting and Review

 

Maintenance Contractor to make entries in service
diary.
Site Owner to review service diary annually.

 

 
Log in to download the original file

Stormwater Management Plan.pdf · 11.7 MB (very large file)

Very large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.