Stormwater Management Plan
The original of this document is very large (11.7 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.
This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).
Log in to see the plans as drawn1.0 INTRODUCTION
This report is lodged in support of a Change application by Calile Malouf
Investments to Noosa Council seeking to develop a hotel at Lots 10 and 11
SP195871, Serenity Close, Noosa Heads.
The proposed development follows four stages of residential unit buildings
developed by Cape Bouvard over the greater Settlers Cove site with Alta
Engineers having completed stormwater design, inspection and
certification for all previous stages.
Design solutions presented in this report are consistent with those previously
adopted with minor refinements borne of experience.
2.0 EXISTING CONDITIONS
The subject site is currently undeveloped and supports vegetation subject to
assessment and recommendations by the Ecological Consultant.
The site falls at moderate grades away from Serenity Close towards an
existing concrete pedestrian path with constructed and natural wetlands areas
to the south.
The entire site consists of loose, poorly graded dune sand and as such
contains no defined overland drainage paths since rainwater infiltrates
directly through the permeable surface.
Stormwater and sewer lines within Easements R, S and F roughly bisect the
site adjacent the existing boundary between lots 10 and 11.
In order to make way for the proposed building footprint, the sewer will need
to be relocated to the Serenity Close Road Reserve with stormwater dealt with
as set out later in this report, including a realigned emergency overflow pipe
located beneath the building in a volumetric easement.
Refer detail survey at Appendix E.
__________________________________________________________________________
A6769/22/SWMP/RevA October 2022 Page 1 of 6
SH/PL
Brah101 Pty Ltd t/as ALTA PROJECTS
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.