Delegated Report - Code - Planning OPW25 0206 (As Pubished) · OPW25/0206
CURRENCY PERIOD
2. The Currency Period for this development approval lapses if the development has not
substantially started by 12 June 2028, unless an application to extend the currency period is
approved by Council.
PRIOR TO COMMENCEMENT OF WORKS
3. Prior to requesting a prestart meeting:
a. Tree protection measures must be installed under the supervision of the Project
Arborist. (Refer to Retention of Existing Trees Conditions)
b. A pre-clearance survey must be undertaken to clearly identify all trees to be removed
and those to be retained on the site, in accordance with the approved plans and
documents of this Decision Notice.
c. A Tree Protection Bond of $50,000 must be submitted to Council in the form of cash or
an unconditional bank guarantee. The bond is required to secure compliance with
conditions of this approval relating to vegetation clearing and the protection of retained
trees identified on the approved plans and supporting documentation, including the
establishment and maintenance of tree protection measures and prevention of damage
to retained native vegetation.
d. Certificates demonstrating currency of public liability insurance and works insurance
covering the works must be submitted to Council prior to the prestart meeting.
e. A fauna and habitat pre-clearance survey including a fauna trapping program is to be
conducted within 2 weeks of commencement of clearing works, in accordance with the
requirements outlined in the approved Fauna Management Plan.
f. Provide written evidence of compliance with SARA referral agency response, condition
5 (SARA reference 2602-50749 SRA)
*(Refer to Advisory Note
4. A prestart meeting must be organised with Council’s delegate by calling 5329 6500 (giving
at least five business days’ notice). The prestart meeting must be attended by the responsible
persons for:
a. Arboreal works
b. Fauna management works
c. Erosion and sediment control works
d. Other relevant parties
DURING WORKS
General
5. Where damage occurs to any Council asset as a result of the development works, it must be
repaired immediately where it creates a hazard that presents risk to person or property. Other
damage must be repaired prior to completion of works.
6. All works must be constructed and work procedure undertaken in accordance with:
a. The approved plans/documents and conditions detailed in this Decision Notice.
b. The relevant conditions of the higher order Material Change of Use approval viz.
Planning and Environment Court Judgment No. 3746 of 2023, to which this approval
relates.
Page 10 of 15
Document Set ID: 24805097
Version: 3, Version Date: 11/06/2026
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Delegated Report - Code - Planning OPW25 0206 (As Pubished).pdfRelated documentApplication case desk ↗
About this file
- File size
- 1.6 MB (small file)
- File type
No other editions are linked here.