OPERATIONAL PLAN 2020-21 PROGRESS REPORT
THE NOOSA ENVIRONMENT
No. Project Responsibility Update PS FLT)
1 Continue the implementation of Council's Fire Director Environment & Sustainable Council is currently implementing on-ground actions related to our existing fire On track Qo
Management Plans Development management plans. A new Bushland Reserve Fire Management Plan is being
drafted to replace the 2015 plan, and is expected to be available for public
comment in February 2021. Site-specific multi-agency plans for some of our
highest risk sites are also being developed, to further complement and
strengthen our existing actions. All are expected to be in place in preparation
for works in the lead-up to the next fire season.
2 Implement the Noosa Environment Strategy Environmental Services Manager With an adopted Environment Strategy, appropriate monitoring mechanisms On track Qo
are now being put in place for implementation and actions are progressing.
The first annual report on the progress of the Implementation Plan of the
Environment Strategy was reported to Council in August 2020.
3 Adopt the Noosa River Management Plan and commence Environmental Services Manager Feedback from both previous Draft River Plan consultation periods has been Behind Schedule @
implementation collated and was reported to Council in January 2021. A Stakeholder
Reference Group is being developed in partnership with Maritime Safety
Queensland, with an Expression of Interest to join in February 2021. This
stakeholder group will support the finalisation and implementation of the Plan,
as well as the resolution of other long-standing issues associated with the
Noosa River.
4 Continue to implement and undertake a review of Zero Director Environment & Sustainable The 2019/20 Carbon Footprint for Noosa Council was reported to Council in On track go
Emissions Noosa (ZEN) Strategy and Action Plan Development December 2020. Further solar installations are planned for small sites. A
Councillor workshop is scheduled for March 2021 to consider pathways to net
zero emissions by 2026.
5 Finalise the strategic review of landfill emission reduction Waste and Environmental Health Fill plan adapted to to ensure that interim level reached ahead of schedule so On track a
Opportunities Manager additional methane extraction wells can be installed in March 2021. Extensive
capping works to prevent fugitive emissions to be completed as part of capital
works over the next 18 months. LFG contractor (LMS) current exploring
options to utilise methane for power generation on site.
6 Continue to partner with The Nature Conservancy to Director Environment & Sustainable The project plan was reported to Council in July 2020 and the first annual Behind Schedule @
implement the Oyster Reef Restoration Project in the Development report in September. The project is progressing well, despite COVID
Noosa River restrictions on bringing the community together around the project, and the
Project Manager has had extensive one-on-meetings with key stakeholders,
and public information sessions were held in December.
7 Continue the implementation of the Yurol and Ringtail Chief Executive Officer The Transition Committee met on 10 December 2020. The harvesting Ontrack @
Forestry Project schedules for the pine plantations have been delayed due to China's boycott
of Australian timber products. The harvesting of the hardwood areas (which
depend on local markets) are on track. Negotiations continue with Greenfleet
to undertake a broad scale regeneration project and that is expected to come
to fruition within the next 3 to 4 months.
Page 89 of 100See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.