OPERATIONAL PLAN 2020-21 PROGRESS REPORT
THE NOOSA COMMUNITY
No. Project ky felting Update PELE)
1 Support the community in the ongoing recovery efforts Director Community Services Support from across organisation continuing for businesses, residents and On track @
from COVID-19 community organisations. Successful festive season particuarly the Christmas
Convoy.
2 Support the community in the ongoing recovery efforts Director Community Services Appointment of temp. Community Development Officer - Recovery, has been On track @
from the bushfires made. Work plan developed and a number of initiatives completed inc First
Year Anniversary events at Peregian, Cooroibah and North Shore
3 Continue with the design and construction of Stage 3 of Director Community Services Tender for new Community House and Greenspace closed. Evaluation of Behind Schedule @
the Rufous Street project including the construction of the tender responses complete. Tender report adoped by Council.
new Peregian Beach Community House
4 Review options for mobile/outreach library services Libraries & Galleries Manager Councillor workshop undertaken 23/09/2020; Community consultation on On track @
proposed model undertaken Nov-Dec. Council report seeking endorsement
of proposed model in Feb.
5 Progress implementation of Master Plans for the Noosa Community Development Manager Noosa District - Prelimimary plans for link road complete; detailed design On track @
District Sports Complex and the Cooroy Sports Complex commenced; concept plans for wellbeing hub developed; lighting installed at
Cricket, Rugby League and Touch Football; second field relocated for Rugby
League. Cooroy - external funding sought for lighting; consultation with clubs
on amenities/clubhouse redevelopment.
6 Implement a new Heritage Portal Heritage Coordinator Contract awarded, planning and development workshops completed. On track @
7 Develop a new Waste Management Strategy Waste and Environmental Health Contract to develop startegy awarded to Mike Ritchie and Associates. On track @
Manager Scoping of staging of strategy production has been agreed and relevent
Council data provided. Work on the strategy currently underway. Public
consultation likely to start in February-March 2021.
Page 90 of 100See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.