2025 DISASTER RECONSTRUCTION FUNDING ARRANGEMENTS - EMERGENCY RECONSTRUCTION WORKS FOR THE NOOSA COUNCIL ROAD AND INFRASTRUCTURE NETWORK · Special Meeting Report

of 5

Page text shows just the words. Original shows the document exactly as it was published.

SPECIAL MEETING                                                                             21 MAY 2025



Further to this phase of the project, the Project Team is developing a submission to the Queensland
Reconstruction Authority (QRA) for a further $20m to $30m of asset repairs using Reconstruction of
Public Assets (REPA) grant funds. The procurement and contract awards for these works will be as
per standard Council Policy and procedure.

2. Project Timelines
The deadline for work to be completed under this grant is 3 months from the date of the event. This
means the repair works to the roads need to commence as soon as possible and be finished by 29
June, 2025 to ensure cost recovery is not compromised.

3. Next Steps
      •   Award delegation to the CEO so emergency road repairs can commence as a priority.
      •   Source and award contracts to suitable suppliers who have the capability and capacity to
          make the necessary repairs to the road.
      •   Have contractors commence and complete the works by 29 June, 2025 to ensure cost
          recovery.

Link to Corporate Plan

Theme No. 2 - Liveability
Liveability encompasses housing, facilities and services, transport, health and wellbeing to enable
an inclusive, connected and vibrant community.
Objective 2.7
Fund and deliver sustainable assets and facilities and associated services, responding to the
changing needs of the community and the challenges and opportunities of the future.


Previous Council Consideration
Nil

Finance
Emergency Works and Immediate Recovery Works are eligible under the DRFA program where they
are eligible, are completed within the deadline and suitable evidence is available. This means all
costs expensed for these works are eligible for cost recovery.

Emergency Works deadline is 3 months from the date of event. This means the repair works to roads
need to commence as soon as possible and be finished by 29 June 2025.


Risk & Opportunities
 Funding Risks                Mitigation
 The funding recovery via     The scope of the work has been deemed acceptable by QRA and therefore
 a grant from QRA is          funding will be covered by the grant.
 compromised.

 Cost Risks                   Mitigation
 The cost       of   works    Standard contract management processes will help ensure cost control is in
 escalates           during   place.
 program.
Log in to download the original file

Special Meeting Report.pdf · 120 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.