2025 DISASTER RECONSTRUCTION FUNDING ARRANGEMENTS - EMERGENCY RECONSTRUCTION WORKS FOR THE NOOSA COUNCIL ROAD AND INFRASTRUCTURE NETWORK · Special Meeting Report
SPECIAL MEETING 21 MAY 2025
To help manage costs, the emergency works for road repair are being
contracted on a day rate and have oversight by supervisors (Council or
Northlane).
Program Risks Mitigation
Contractor availability is The Project Team have identified likely contractors with capacity and
limited due to competing capability to commence works. By being able to award contracts rapidly
disaster works. ensures Council can utilise available limited capacity.
There is the potential Wet weather delays will be managed as required. However, the need to
that the project is award contracts sooner will help ensure deadlines are met.
delayed due to wet
weather.
Resource risk. Resource allocation using services outside Council crews ensures
continuity during this period of labour instability due to protected Union
action.
When Council staff return to standard work, they will be able to focus on the
backlog of issues that are not Disaster related.
Safety Risks Mitigation
The contractor fails to Prior to commencement of services, the recommended contractor’s
ensure the work is management plans, Safe Work Method Statements, Job Hazard Analysis
conducted safely and in (or similar) and other documentation will be submitted, reviewed, and
accordance with minimum accepted by Council.
standards. Council will undertake surveillance, regular safety audits and inspections
throughout the construction period.
Environmental Harm Mitigation
Risks
Works impact on the The contractor is responsible for the development and implementation of
environment. strategies to minimise impacts such as noise, dust, vibration, sediment
and erosion. The superintendent and Council staff will closely monitor the
construction phase to ensure all impacts are minimised.
Council can offer the contractor examples of the expected environmental
plans to support their development.
Public Disruption Risks Mitigation
Traffic disruption due to Interruption due to these works is no different to any other similar works
road works. executed within the shire.
Community feedback to Customer Service indicates that the disruption of
roads damaged by the 29 March 2025 event are impacting their safe
travel.
Communication issues. The Disaster Reconstruction Coordinator will work closely with Council’s
Communications and Infrastructure departments, as well as the contractor
to provide necessary communication support if and when needed.
Human Rights
Human Rights Compatibility Statement
In developing this Report, the subject matter has been considered in accordance with the
requirements of the Queensland Human Rights Act 2019. It is considered that the subject matter
does not conflict with any human rights and supports a human rights approach to decision making
by Council. Council representatives will endeavour to act and make decisions under this report in a
manner that is compatible with human rights. This report should be read in conjunction with
Council’s Human Rights Policy.