Stormwater Drainage (Quantity & Quality)
61. A suitably qualified Registered Professional Engineer, specialising in hydraulics
shall prepare engineering drawings and specifications for stormwater designs
and shall be submitted in conjunction with an application for a Development
Permit for Operational Works.
62. Stormwater pipelines within the site shall cater for 10% AEP storm event and
secondary flow paths shall be provided within the site to cater for 1% AEP
storm event.
63. The development must not adversely impact on the existing drainage conditions
on other properties. The applicant must demonstrate that all stormwater runoffs
from the fully developed site must be maintained at predevelopment rates for all
storm events up and including 1% AEP storm event.
64. Stormwater runoff generated from the development must be treated to achieve
the Water Quality Objectives as specified under Healthy Waterways Water
Sensitive Urban Design – Technical Guidelines for South East Queensland
(2006) as well as the State Planning Policy 2014 (SPP 2014) prior to release off
site. For the purpose of this condition, treatment of waters from catchments B1
and C1 as shown on Drawing B14158.W-SK100 A by Calbre Consulting, dated
050/2/16 shall be considered as part of the development to determine mitigation
requirements and load reduction targets.
If detailed design demonstrates insufficient footprint is available for the water
quality treatment devices to achieve the pollutant reduction targets of 80%
reduction in Total Suspended Solids, 60% reduction in Total Phosphorous, and
45% reduction in Total Nitrogen compared to an unmitigated development, the
applicant must increase available space to ensure the water quality objectives
can be achieved.
65. Stormwater Quality Treatment must be designed in accordance with the Water
by Design MUSIC modelling Guidelines. Any deviation away from the
recommendations of the Water by Design guidelines may only be approved
where:
65.1. letters signed by the authors of the Water by Design MUSIC modelling
guidelines and/or eWater MUSIC modelling program are provided to
confirm that the modelled design is expected to meet the required water
quality outcomes at the discharge point of the site; and
65.2. a contingency plan to monitor for and to remove cyanobacterial and algal
outbreaks from waterbodies, including costs, is provided for approval with
the Operational Works application and the approved version is
implemented throughout the lifetime of the development. All stormwater
runoff treatment must be undertaken within the development areas of the
site. Stormwater likely to contain grease and oil (i.e. from all roads and
car parking areas) shall be managed via grease and oil arrestors prior to
treatment within bioretention basins, wetlands and water quality control
ponds.
Page 11 of 19
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.