6. The requirements for the associated Reconfiguration of a Lot approval included
in this permit must be completed and Endorsement of the Plan of Survey by
Council must be obtained prior to any commencement of any use approved by
this Development Permit.
7. The Development Permit for a material change of use lapses if the use has not
commenced by 21 July 2020. The uncompleted aspects of this development
approval lapse if the whole of the approved use has not happened by 21 July
2024.
Staging
8. The development may be staged in accordance with the approved plan titled
“Staging Plan” CO-000-2014 Sheet 02/02 Revision H dated 13 November 2015
(as annotated by Council) and as follows:-
8.1. The following works shall be undertaken and completed prior to the
commencement of use of Stage 1a:
8.1.1. All roadworks on the Main Road of Cooroy Connection Road (Elm
Street) including the upgrading works for the road intersections with
Pearsons Road, linemarking and pedestrian refuge crossing, as
required by conditions of this approval.
8.1.2. All frontage works including footpaths and landscaping for Trading
Post Road, Pearson Road and Elm Street as required by conditions
of this approval.
8.1.3. A Bus stop and shelter on the eastern side of Elm Street as
required by conditions of this approval.
8.1.4. A Bus stop and shelter on the western side of Elm Street as
required by conditions of this approval.
8.1.5. A pedestrian refuge crossing and lighting associated with the bus
stop pair on Elm Street.
8.1.6. All fencing to Trading Post Road and Pearson Road, and all
acoustic fencing to Elm Street as required by the approved Acoustic
Report.
8.1.7. Landscaping treatments to open space areas associated with Stage
1a including the establishment and rehabilitation of all detention
basins, the establishment of landscaping buffers to site boundaries
and adjoining residential properties and street trees.
8.2. The following works shall be undertaken and completed prior to the
commencement of use of Stage 4:
8.2.1. All roadworks, access and frontage works and landscaping for
Lamonts Road as required by conditions of this approval.
8.2.2. All fencing to Lamonts Road.
Page 4 of 19
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.