Delegated Report - Code - Planning OPW25 0121 (As Published)
i. Qualified experienced Civil Engineer (RPEQ) confirming design intent and
conformance with applicable standards and specifications, along with the
relevant descriptions of assets, services and structures and;
ii. Registered Cadastral Surveyor (Qld) in regard to the cadastral and locational
information, levels and applicable survey datum.
d. The data must be in accordance with Council’s “Planning Scheme Policy 6 –
Engineering Design Standards”, and fully detail the levels for all engineering works
including but not limited to the drainage network and structures, finished ground and
pavement surface levels.
e. Landscaping, including all assets and improvements within parks, open space and road
reserves areas are to be shown on an accompanying separate landscape plan
(prepared in .dwg file format with accompanying hardcopy PDFs) and include a
complaint ADAC XML file. Details of the landscaping and all associated assets and
improvements may be included in the ADAC XML digital file prepared for associated
civil infrastructure, or alternatively, be provided as a separate ADAC XML digital file
containing landscape and asset information only.
On Maintenance
73. All municipal works must be accepted as ‘On Maintenance’ by Council in accordance with
Council’s Planning Scheme Policy 6 prior to plan sealing.
To achieve ‘On Maintenance’ status:
a. the supervising RPEQ must submit to Council for review and acceptance:
i. certification that all works have been undertaken and completed in accordance
with the requirements of this approval;
ii. As Constructed details in accordance with Council’s Planning Scheme Policy;
and
iii. maintenance and operational manuals for all proprietary or site-specific devices.
b. Council must inspect and agree to accept the municipal works as ‘On Maintenance’.
Any defect or substandard work observed by Council during the inspection must be
rectified to the satisfaction of Council prior to Council’s acceptance of the ‘On
Maintenance’ status.
(*) Refer to Advisory Note
c. A maintenance bond must be submitted to Council in accordance with Council’s
Planning Scheme Policy 6. The maintenance bond shall be 5% of the agreed value of
the municipal works to become ‘On Maintenance’ or $2,000 (whichever is greater).
Off Maintenance
74. Prior to requesting an Off Maintenance inspection, the developer must provide a written
request for the Off Maintenance inspection.
75. A re-inspection fee in accordance with Council’s Fees and Charge Register will be charged
where:
a. a Council inspection reveals works do not comply with approval requirements; or
b. submitted certification falsely states works comply with approval requirements.
LANDSCAPING
Supervision/Certification
76. Prior to the sealing of the survey plan the following (prepared by respective qualified persons*
and certifying compliance with approvals) must be submitted to Council:
Page 18 of 22
Document Set ID: 24187118
Version: 9, Version Date: 04/12/2025
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the original