Delegated Report - Code - Planning OPW25 0121 (As Published)
8. Council reserves the right to stop and start the maintenance period depending on
performance.
Bonds must:
a. meet the requirements of Council’s Planning Scheme Policy 4 Performance Bonds and
Planning Scheme Policy 6 Engineering Design Standards;
b. be calculated based on an agreed schedule of works (for Maintenance Bonds only);
c. be lodged to Council with the relevant bond administration fee(s); and
d. be requested for release by writing to Council when relevant approval requirements
have been met.
PRIOR TO COMMENCEMENT OF WORKS
9. All necessary approvals from external service providers (e.g., Unitywater, Energex and NBN)
and external parties on which the development works are proposed have been obtained and
a copy supplied to Council.
10. Copies of the approved plans, duly signed by the consultant Registered Professional
Engineer of Queensland (RPEQ) must be provided to Council’s Engineering Officer
Construction at the “pre start” meeting.
11. A condition report including photographs of the frontage of the site must be completed and
submitted to council at the prestart meeting / prior to any works commencing.
12. Certificates demonstrating currency of public liability insurance and works insurance covering
the works must be submitted to Council prior to the prestart meeting.
13. Council must be contacted at least 5 working days prior to any works commencing to
organise a prestart. The contact number to arrange a pre-start meeting is 5329 6500. The
pre-start meeting must include the relevant parties for the following aspects of the works:
a. Civil engineering works;
a. Landscape works;
b. Arboreal works;
c. Erosion and sediment control works; and
d. Other relevant parties.
14. A Construction Management Plan must be submitted to Council prior to the pre-start meeting
and must specifically address the following:
a. Traffic Management during all aspects of the construct phase including:
i. A Traffic Management Control Plan in accordance with Manual of Uniform
Traffic Control Devices (MUTCD) detailing all temporary signage and traffic
control measures prior to construction;
ii. Maintenance of safe vehicle and pedestrian access across the frontage of the
site both during daily construction and after daily construction has ceased;
iii. Proposed fencing to the site during the construction phase of the development;
iv. Adequate parking arrangements for construction workers; and
v. No queuing of trucks is permitted on residential streets, especially prior to
7.00am. Further parked trucks must have engines turned off.
b. Maintenance and protection of water quality and existing drainage lines through the
construction site through the implementation of appropriate erosion and sediment
control measures;
c. Works programme identifying key components of the works and their respective
durations;
Page 8 of 22
Document Set ID: 24187118
Version: 9, Version Date: 04/12/2025