Site Access for vehicles – a Traffic Management Plan will be established by the contractor and project
team to coordinate the delivery processes for materials as well as the daily operational workings of the
site, including sub-contractor parking either on or off the site, with a shuttle bus service being provided
where necessary.
Waste Management Practices: Waste management facilities will be conveniently located away from
sensitive vegetation and watercourses. A regular schedule for waste collection and disposal will be
implemented to avoid accumulation, with recycling encouraged to reduce landfill waste. Clearly marked
waste storage areas will facilitate effective waste segregation. These will be located to the north of the
carpark closest to the main road entry for easy access.
Ablution Facilities: In addition to the main site set-up and the semi-permanent ablution facilities located
there, Mobile/Temporary ablution facilities will be strategically placed within the footprint of Cabins 12 &13,
ensuring easy access for servicing and for construction workers to limit pedestrian movement across the
site. It is envisaged that these could be on small self-supporting trailers to reduce the ground surface
touching and for easy removal/maintenance. These portable amenities will be available throughout the
project, regardless of the number of workers on site.
Laydown Areas:
The establishment of well-defined laydown areas is crucial for efficient construction and minimizing
environmental impact, careful planning is therefore required.
The proposed carpark area at the northern end of the site offers a suitable location for primary delivery
and laydown areas due to its ample space. The edge of this area adjacent to retained trees will require
ground protection and/or exclusion from material storage.
The footprint for Cabins 12-15 may offer additional laydown areas for materials delivered on-site due to its
proximity to access roads. However, coordination with the existing RACV Resort may be required to avoid
disrupting visitor access, which can be managed.
Laydown areas will be strategically located to ensure efficient construction operations whilst minimizing
environmental impact. Refer to ATTACHMENT D for proposed locations.
Several key considerations for managing laydown areas effectively include the below – these will be part
of the main contractor's site management planning:
o Clearly defined boundaries
o Ground protection measures adjacent to retained trees (physical surface treatments, geotextiles,
mulch)
o Efficient material organization
o Designated waste storage areas with regular removal schedules
o Safety measures (signage, lighting, barriers)
o Environmental protection (avoiding spills, leaks, and littering)
6
Construction and Tree Management Plan - REV03 Page of 45
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Approved Document Construction & Tree Management Plan OPW25-0206.pdfRelated documentApplication case desk ↗
About this file
- File size
- 10.8 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.